JOINT STRUCTURE OF STEEL PIPE COLUMN
To maintain strength of a joint structure for connecting steel pipe columns while reducing weld parts as much as possible.SOLUTION: A joint structure of a steel pipe column includes a first diaphragm disposed on one end of a first steel pipe column, a first flange fixed to the first diaphragm, a second diaphragm disposed on one end of a second steel pipe column, a second flange fixed to the second diaphragm, and a first doubling plate. The first steel pipe column and the second steel pipe column are disposed one above the other along a material axis direction. The first flange and the second flange are connected with bolts through the first doubling plate. A first open hole capable of being used as a hand hole is disposed either one of the first flange or the second flange.SELECTED DRAWING: Figure 1
【課題】鋼管柱を繋ぐ継手構造において、溶接部分を極力少なくしつつ、強度を保つことを目的とする。【解決手段】鋼管柱の継手構造は、第1の鋼管柱の一端に設けられた第1のダイアフラムと、第1のダイアフラムに固定された第1のフランジと、第2の鋼管柱の一端に設けられた第2のダイアフラムと、第2のダイアフラムに固定された第2のフランジと、第1の添え板とを含み、第1の鋼管柱と第2の鋼管柱とが材軸方向に沿って上下に配置され、第1のフランジと第2のフランジとが第1の添え板でボルト接合され、第1のフランジ及び第2のフランジの一方に、ハンドホールとして用いることのできる第1の貫通孔が設けられている。【選択図】図1
JOINT STRUCTURE OF STEEL PIPE COLUMN
To maintain strength of a joint structure for connecting steel pipe columns while reducing weld parts as much as possible.SOLUTION: A joint structure of a steel pipe column includes a first diaphragm disposed on one end of a first steel pipe column, a first flange fixed to the first diaphragm, a second diaphragm disposed on one end of a second steel pipe column, a second flange fixed to the second diaphragm, and a first doubling plate. The first steel pipe column and the second steel pipe column are disposed one above the other along a material axis direction. The first flange and the second flange are connected with bolts through the first doubling plate. A first open hole capable of being used as a hand hole is disposed either one of the first flange or the second flange.SELECTED DRAWING: Figure 1
【課題】鋼管柱を繋ぐ継手構造において、溶接部分を極力少なくしつつ、強度を保つことを目的とする。【解決手段】鋼管柱の継手構造は、第1の鋼管柱の一端に設けられた第1のダイアフラムと、第1のダイアフラムに固定された第1のフランジと、第2の鋼管柱の一端に設けられた第2のダイアフラムと、第2のダイアフラムに固定された第2のフランジと、第1の添え板とを含み、第1の鋼管柱と第2の鋼管柱とが材軸方向に沿って上下に配置され、第1のフランジと第2のフランジとが第1の添え板でボルト接合され、第1のフランジ及び第2のフランジの一方に、ハンドホールとして用いることのできる第1の貫通孔が設けられている。【選択図】図1
JOINT STRUCTURE OF STEEL PIPE COLUMN
鋼管柱の継手構造
TAHARA KENICHI (author) / SASAKI SATOSHI (author)
2023-12-12
Patent
Electronic Resource
Japanese
IPC:
E04B
Allgemeine Baukonstruktionen
,
GENERAL BUILDING CONSTRUCTIONS