CRUSHER AND REMOVAL METHOD OF COLUMNAR IMPROVEMENT PILE
To provide a crusher and a removal method of a columnar improvement pile which enable stable crushing work without misalignment of a columnar improvement pile embedded in the ground.SOLUTION: A crusher 100 includes a crushing rod 10 having a cylindrical rod body 4 having a jetting port 41 at the tip and a head 5, a compressor 7 for supplying air jetted from the jetting port 41, and drive devices 2, 3 for rotating and lifting the crushing rod 10, and crushes a columnar improvement pile 6 embedded in the ground, wherein the head 5 has a guide 50 and crushing teeth 52, the guide 50 has a side face in a circular truncated cone shape that a trajectory drawn when the crushing rod 10 is rotated is end-widened in an excavation direction, and is fixed to the rod body 4 so that the jetting port 41 is arranged in the trajectory of the guide 50.SELECTED DRAWING: Figure 1
【課題】本開示は、地中に埋設された柱状改良杭を芯ずれすることなく安定して破砕作業を行うことができる破砕装置及び柱状改良杭の撤去工法を提供することを目的とする。【解決手段】本開示に係る破砕装置100は、先端部に噴出口41を有する円筒状のロッド本体4とヘッド5とを有する破砕ロッド10と、噴出口41から噴射される空気を供給するコンプレッサ7と、破砕ロッド10を回転・昇降させる駆動装置2,3と、を備え、地中に埋設された柱状改良杭6を破砕する破砕装置であって、ヘッド5は、ガイド50と破砕歯52とを有し、ガイド50は、破砕ロッド10を回転時に描く軌跡が掘削方向に向けて末広がりの円錐台側面形状となっており、かつ、噴出口41がガイド50の軌跡内に配置されるようにロッド本体4に固定されている。【選択図】図1
CRUSHER AND REMOVAL METHOD OF COLUMNAR IMPROVEMENT PILE
To provide a crusher and a removal method of a columnar improvement pile which enable stable crushing work without misalignment of a columnar improvement pile embedded in the ground.SOLUTION: A crusher 100 includes a crushing rod 10 having a cylindrical rod body 4 having a jetting port 41 at the tip and a head 5, a compressor 7 for supplying air jetted from the jetting port 41, and drive devices 2, 3 for rotating and lifting the crushing rod 10, and crushes a columnar improvement pile 6 embedded in the ground, wherein the head 5 has a guide 50 and crushing teeth 52, the guide 50 has a side face in a circular truncated cone shape that a trajectory drawn when the crushing rod 10 is rotated is end-widened in an excavation direction, and is fixed to the rod body 4 so that the jetting port 41 is arranged in the trajectory of the guide 50.SELECTED DRAWING: Figure 1
【課題】本開示は、地中に埋設された柱状改良杭を芯ずれすることなく安定して破砕作業を行うことができる破砕装置及び柱状改良杭の撤去工法を提供することを目的とする。【解決手段】本開示に係る破砕装置100は、先端部に噴出口41を有する円筒状のロッド本体4とヘッド5とを有する破砕ロッド10と、噴出口41から噴射される空気を供給するコンプレッサ7と、破砕ロッド10を回転・昇降させる駆動装置2,3と、を備え、地中に埋設された柱状改良杭6を破砕する破砕装置であって、ヘッド5は、ガイド50と破砕歯52とを有し、ガイド50は、破砕ロッド10を回転時に描く軌跡が掘削方向に向けて末広がりの円錐台側面形状となっており、かつ、噴出口41がガイド50の軌跡内に配置されるようにロッド本体4に固定されている。【選択図】図1
CRUSHER AND REMOVAL METHOD OF COLUMNAR IMPROVEMENT PILE
破砕装置及び柱状改良杭の撤去工法
AMAGAI TAKASHI (author)
2024-01-18
Patent
Electronic Resource
Japanese
IPC:
E02D
FOUNDATIONS
,
Gründungen
COMBINED (PILE-SLAB, PILE-BELT, PILE-COLUMNAR) FOUNDATION ERECTION METHOD