BEAM CONSTRUCTION METHOD, BEAM, AND HALF-PRECAST MEMBER
To provide a beam construction method for constructing a large-section reinforced concrete beam without using timbering, and to provide a beam and a half-precast member.SOLUTION: A beam 20 comprises multiple half precast members 21, 22, 23 that form the lowest part. Each of the half precast members 21 to 23 is divided in a width direction D2 of the beam 20, and has a block portion made of concrete having a length in an axial direction D1 of the beam 20. The beam 20 comprises a plurality of tie bars 25 and a plurality of beam side face axial bars 26. The tie bars 25 are arranged near upper surfaces of the half precast members 21 to 23 so as to extend in the width direction D2 of the beam 20 for a length spanning all of the half precast members 21 to 23 that constitute the beam 20. The beam side face axial bars 26 are arranged vertically spaced apart near the side face of the beam 20. The beam 20 has an upper portion, which is a cast-in-place concrete portion 29, which is an area having a height H2 that is equal to or more than a half of a height H1 of the beam 20.SELECTED DRAWING: Figure 1
【課題】支保工を用いずに大断面の鉄筋コンクリート造の梁を施工するための梁の施工方法、梁及びハーフプレキャスト部材を提供する。【解決手段】梁20は、最下部を構成する複数のハーフPCa部材21,22,23を備える。各ハーフPCa部材21~23は、梁20の幅方向D2に分割され、梁20の軸方向D1の長さのコンクリートで構成されたブロック部を有する。梁20は、複数のつなぎ筋25及び複数の梁側面軸方向筋26を備える。つなぎ筋25は、ハーフPCa部材21~23の上面近傍において、梁20を構成する全てのハーフPCa部材21~23に渡る長さで、梁20の幅方向D2に延在するように配置される。梁側面軸方向筋26は、梁20の側面近傍において、垂直方向に離間して配置される。梁20は、上部であって、梁20の高さH1の半分以上の高さH2を有する領域である現場打設コンクリート部29を有する。【選択図】図1
BEAM CONSTRUCTION METHOD, BEAM, AND HALF-PRECAST MEMBER
To provide a beam construction method for constructing a large-section reinforced concrete beam without using timbering, and to provide a beam and a half-precast member.SOLUTION: A beam 20 comprises multiple half precast members 21, 22, 23 that form the lowest part. Each of the half precast members 21 to 23 is divided in a width direction D2 of the beam 20, and has a block portion made of concrete having a length in an axial direction D1 of the beam 20. The beam 20 comprises a plurality of tie bars 25 and a plurality of beam side face axial bars 26. The tie bars 25 are arranged near upper surfaces of the half precast members 21 to 23 so as to extend in the width direction D2 of the beam 20 for a length spanning all of the half precast members 21 to 23 that constitute the beam 20. The beam side face axial bars 26 are arranged vertically spaced apart near the side face of the beam 20. The beam 20 has an upper portion, which is a cast-in-place concrete portion 29, which is an area having a height H2 that is equal to or more than a half of a height H1 of the beam 20.SELECTED DRAWING: Figure 1
【課題】支保工を用いずに大断面の鉄筋コンクリート造の梁を施工するための梁の施工方法、梁及びハーフプレキャスト部材を提供する。【解決手段】梁20は、最下部を構成する複数のハーフPCa部材21,22,23を備える。各ハーフPCa部材21~23は、梁20の幅方向D2に分割され、梁20の軸方向D1の長さのコンクリートで構成されたブロック部を有する。梁20は、複数のつなぎ筋25及び複数の梁側面軸方向筋26を備える。つなぎ筋25は、ハーフPCa部材21~23の上面近傍において、梁20を構成する全てのハーフPCa部材21~23に渡る長さで、梁20の幅方向D2に延在するように配置される。梁側面軸方向筋26は、梁20の側面近傍において、垂直方向に離間して配置される。梁20は、上部であって、梁20の高さH1の半分以上の高さH2を有する領域である現場打設コンクリート部29を有する。【選択図】図1
BEAM CONSTRUCTION METHOD, BEAM, AND HALF-PRECAST MEMBER
梁の施工方法、梁及びハーフプレキャスト部材
SAITO MOTOTSUGU (author) / NAGAYA KEIICHI (author) / TANAKA YOSHIKAZU (author) / INUI TOMOHIRO (author)
2024-09-09
Patent
Electronic Resource
Japanese
CONSTRUCTION METHOD OF HALF-PRECAST CONCRETE MEMBER, FRAME STRUCTURE AND REINFORCED CONCRETE BEAM
European Patent Office | 2024
|HALF PRECAST MEMBER, AND MANUFACTURING METHOD OF HALF PRECAST MEMBER