A platform for research: civil engineering, architecture and urbanism
Construction equipment and construction method of underground watertight wall
The present invention relates to a ground excavation and amelioration apparatus which continuously buries concrete piles in a peristyle method underground and forms a cutoff wall, and an underground cutoff wall construction method using the same and, more specifically, relates to a ground excavation and amelioration apparatus which connects concrete piles and an on-site-placed wedge-type cutoff wall which blocks a gap between concrete piles which are buried at regular intervals and strengthens the ground, and which makes a perfect cutoff possible with a cutoff wall such as a soil cement wall (SCW); and an underground cutoff wall construction method using the same. The apparatus of the present invention comprises an excavation unit with a protruding screw wing mounted on a bottom end of an auger rod of an excavator wherein a hammer with an air hole is installed. In the protruding screw wing on the external surface of the excavation unit formed is a mortar injection passage connected to a mortar injection pipe in the auger rod. As such, the mortar supplied to the mortar injection pipe of the screw is supplied through the mortar injection passage of the screw wing.
본 발명은 지중에 콘크리트 파일을 주열식으로 연속 매설하여 지하 차수벽을 형성하는 지반 굴착 및 개량 장치 및 이를 이용한 지하 차수벽 시공방법에 관한 것으로 더욱 상세하게는 일정 간격으로 매설된 콘크리트 파일 사이에 간격을 차단하고 지반을 강화하는 현장 타설 쐐기형 차수벽을 콘크리트 파일과 일체가 되도록 연결 형성하여 소일 시멘트 월(SCW)과 같은 차수벽으로 완벽한 차수를 할 수 있게 한 지반 굴착 및 개량 장치 및 이를 이용한 지하 차수벽 시공방법에 관한 것이다. 본 발명은 굴착기의 오거로드의 하단에 스크류 날개를 돌설시킨 굴착유닛을 장착하여 이의 내부에 에어공을 형성한 해머를 설치한 것에 있어서, 상기 굴착유닛의 외면에 돌설된 스크류 날개의 내부에 오거로드의 내측의 몰탈주입관과 연결되는 몰탈 주입통로를 형성하여 스크류의 몰탈주입관으로 공급되는 몰탈을 스크류 날개의 몰탈 주입통로를 통해 공급되게 함을 특징으로 한 지하 차수벽 시공장치와 상기 지하 차수벽 시공장치를 이용한 지하 차수벽 사공방법을 특징으로 한다.
Construction equipment and construction method of underground watertight wall
The present invention relates to a ground excavation and amelioration apparatus which continuously buries concrete piles in a peristyle method underground and forms a cutoff wall, and an underground cutoff wall construction method using the same and, more specifically, relates to a ground excavation and amelioration apparatus which connects concrete piles and an on-site-placed wedge-type cutoff wall which blocks a gap between concrete piles which are buried at regular intervals and strengthens the ground, and which makes a perfect cutoff possible with a cutoff wall such as a soil cement wall (SCW); and an underground cutoff wall construction method using the same. The apparatus of the present invention comprises an excavation unit with a protruding screw wing mounted on a bottom end of an auger rod of an excavator wherein a hammer with an air hole is installed. In the protruding screw wing on the external surface of the excavation unit formed is a mortar injection passage connected to a mortar injection pipe in the auger rod. As such, the mortar supplied to the mortar injection pipe of the screw is supplied through the mortar injection passage of the screw wing.
본 발명은 지중에 콘크리트 파일을 주열식으로 연속 매설하여 지하 차수벽을 형성하는 지반 굴착 및 개량 장치 및 이를 이용한 지하 차수벽 시공방법에 관한 것으로 더욱 상세하게는 일정 간격으로 매설된 콘크리트 파일 사이에 간격을 차단하고 지반을 강화하는 현장 타설 쐐기형 차수벽을 콘크리트 파일과 일체가 되도록 연결 형성하여 소일 시멘트 월(SCW)과 같은 차수벽으로 완벽한 차수를 할 수 있게 한 지반 굴착 및 개량 장치 및 이를 이용한 지하 차수벽 시공방법에 관한 것이다. 본 발명은 굴착기의 오거로드의 하단에 스크류 날개를 돌설시킨 굴착유닛을 장착하여 이의 내부에 에어공을 형성한 해머를 설치한 것에 있어서, 상기 굴착유닛의 외면에 돌설된 스크류 날개의 내부에 오거로드의 내측의 몰탈주입관과 연결되는 몰탈 주입통로를 형성하여 스크류의 몰탈주입관으로 공급되는 몰탈을 스크류 날개의 몰탈 주입통로를 통해 공급되게 함을 특징으로 한 지하 차수벽 시공장치와 상기 지하 차수벽 시공장치를 이용한 지하 차수벽 사공방법을 특징으로 한다.
Construction equipment and construction method of underground watertight wall
지반 굴착 및 개량 장치 및 이를 이용한 지하 차수벽 시공방법
JEONG JUN YOUNG (author)
2017-05-16
Patent
Electronic Resource
Korean
IPC:
E02D
FOUNDATIONS
,
Gründungen
underground watertight wall construction method for prevention of brittle fracture
European Patent Office | 2025
PRECAST PILE AND CONSTRUCTION METHOD FOR UNDERGROUND WATERTIGHT WALL USING THE SAME
European Patent Office | 2020
|