A platform for research: civil engineering, architecture and urbanism
SACRIFICIAL STEEL PIPE SAVING CAST IN PLACED PILE AND THE CONSTRUCTION METHOD THEREFOR
The present invention relates to an in-situ pile structure for saving sacrificial steel pipes and a construction method thereof. The in-situ pile structure for saving sacrificial steel pipes is installed across an underwater part and a ground part underneath the underwater part and comprises: a geotextile tube pile constructed below and provided with a geotextile tube; and a sacrificial steel pipe pile continuously constructed on the upper side of the geotextile tube pile and provided with a sacrificial steel pipe on the outer edge thereof. An overlapping part, in which the geotextile tube is overlapped with the inside of the sacrificial steel pipe, is included on a portion on which the geotextile tube pile and the sacrificial steel pipe tube are continuously arranged. A latch protrusion provided on the inner circumferential surface of the sacrificial steel pipe of the overlapping part is attached and installed. The geotextile tube pile is used in the ground part and the sacrificial steel pipe pile is used in the underwater part to greatly reduce the amount of sacrificial steel pipes used without damaging safety in comparison to a conventional pile to increase economic efficiency. The latch protrusion is provided on the overlapping part overlapping the geotextile tube pile and the sacrificial steel pipe pile to have excellent steel composite performance.
본 발명은 희생강관 절약형 현장타설 말뚝 구조 및 그 시공방법으로서, 수중부와 상기 수중부 하측의 지반부에 걸쳐서 설치되는 희생강관 절약형 현장타설 말뚝 구조에 있어서, 하측에 시공되는 것으로 외곽에 토목섬유튜브가 구비되는 토목섬유튜브 말뚝; 및 상기 토목섬유튜브 말뚝의 상측에 연속으로 시공되는 것으로 외곽에 희생강관이 구비되는 희생강관 말뚝;을 포함하고, 상기 토목섬유튜브 말뚝과 희생강관 말뚝이 연속되는 부분에는 상기 토목섬유튜브가 상기 희생강관의 내측에 중첩되는 중첩부를 포함하고, 상기 중첩부의 상기 희생강관 내주면에 구비되는 링 형상의 걸쇄턱이 부착설치되는 것으로서, 지반부에는 토목섬유튜브 말뚝을 수중부에는 희생강관 말뚝을 사용함으로써, 기존 말뚝에 비해 안전성을 훼손하지 않으면서도 희생강관의 사용량을 대폭 절감하여 경제성이 증대되고, 토목섬유튜브 말뚝과 희생강관 말뚝을 중첩하는 중첩부에 걸쇄턱을 구비함으로써, 강합성 성능이 우수하다.
SACRIFICIAL STEEL PIPE SAVING CAST IN PLACED PILE AND THE CONSTRUCTION METHOD THEREFOR
The present invention relates to an in-situ pile structure for saving sacrificial steel pipes and a construction method thereof. The in-situ pile structure for saving sacrificial steel pipes is installed across an underwater part and a ground part underneath the underwater part and comprises: a geotextile tube pile constructed below and provided with a geotextile tube; and a sacrificial steel pipe pile continuously constructed on the upper side of the geotextile tube pile and provided with a sacrificial steel pipe on the outer edge thereof. An overlapping part, in which the geotextile tube is overlapped with the inside of the sacrificial steel pipe, is included on a portion on which the geotextile tube pile and the sacrificial steel pipe tube are continuously arranged. A latch protrusion provided on the inner circumferential surface of the sacrificial steel pipe of the overlapping part is attached and installed. The geotextile tube pile is used in the ground part and the sacrificial steel pipe pile is used in the underwater part to greatly reduce the amount of sacrificial steel pipes used without damaging safety in comparison to a conventional pile to increase economic efficiency. The latch protrusion is provided on the overlapping part overlapping the geotextile tube pile and the sacrificial steel pipe pile to have excellent steel composite performance.
본 발명은 희생강관 절약형 현장타설 말뚝 구조 및 그 시공방법으로서, 수중부와 상기 수중부 하측의 지반부에 걸쳐서 설치되는 희생강관 절약형 현장타설 말뚝 구조에 있어서, 하측에 시공되는 것으로 외곽에 토목섬유튜브가 구비되는 토목섬유튜브 말뚝; 및 상기 토목섬유튜브 말뚝의 상측에 연속으로 시공되는 것으로 외곽에 희생강관이 구비되는 희생강관 말뚝;을 포함하고, 상기 토목섬유튜브 말뚝과 희생강관 말뚝이 연속되는 부분에는 상기 토목섬유튜브가 상기 희생강관의 내측에 중첩되는 중첩부를 포함하고, 상기 중첩부의 상기 희생강관 내주면에 구비되는 링 형상의 걸쇄턱이 부착설치되는 것으로서, 지반부에는 토목섬유튜브 말뚝을 수중부에는 희생강관 말뚝을 사용함으로써, 기존 말뚝에 비해 안전성을 훼손하지 않으면서도 희생강관의 사용량을 대폭 절감하여 경제성이 증대되고, 토목섬유튜브 말뚝과 희생강관 말뚝을 중첩하는 중첩부에 걸쇄턱을 구비함으로써, 강합성 성능이 우수하다.
SACRIFICIAL STEEL PIPE SAVING CAST IN PLACED PILE AND THE CONSTRUCTION METHOD THEREFOR
희생강관 절약형 현장타설 말뚝 구조 및 그 시공방법
ROH KYUNG BEOM (author)
2022-10-19
Patent
Electronic Resource
Korean
IPC:
E02D
FOUNDATIONS
,
Gründungen
SACRIFICIAL STEEL PIPE SAVING CAST IN PLACED PILE AND THE CONSTRUCTION METHOD THEREFOR
European Patent Office | 2022
|STEEL PIPE PILE CONSTRUCTION METHOD OF SACRIFICIAL STEEL PIPE CASING PARTIAL PULLOUT
European Patent Office | 2017
STEEL PIPE PILE CONSTRUCTION METHOD OF SACRIFICIAL STEEL PIPE CASING PARTIAL PULLOUT
European Patent Office | 2016
|CIP Construction method of cast-in-placed-pile using steel rebar banding
European Patent Office | 2020
|