CONSTRUCTION METHOD FOR UNDERGROUND PRESTRESSED SUPPORTING STRUCTURE
Disclosed is a construction method for an underground prestressed supporting structure, comprising the steps of: (1) sinking a soldier pile carrying an anchor cable; (2) constructing a top horizontal support; (3) excavating a foundation pit until a set depth for primary excavation is reached, mounting N enclosing purlins within the range, and tensioning the anchor cable to press same against the N enclosing purlins; (4) excavating the foundation pit, mounting the (N+1)th enclosing purlin, and pressing the anchor cable against the (N+1)th enclosing purlin; (5) completing mounting of all enclosing purlins, and casting a bottom plate; (6) removing the enclosing purlins below the K-th top plate, and constructing the K-th top plate; (7) removing the enclosing purlins below the (K-1)th top plate, and constructing the (K-1)th top plate; (8) completing construction of top plates below the Nth enclosing purlin; and (9) releasing the tensioning on the anchor cable, and constructing top plates. According to the present application, supporting parts are replaced with enclosing purlins, the enclosing purlins serve as force transfer parts to form a prestressed soldier pile, and the enclosing purlins and the soldier pipe are formed as one piece, thereby guaranteeing the integrity and stability of a foundation pit supporting system.
L'invention concerne un procédé de construction pour une structure de support précontrainte souterraine, comprenant les étapes consistant à : (1) enfoncer un pieu vertical portant un câble d'ancrage ; (2) construire un support horizontal supérieur ; (3) excaver une fosse de fondation jusqu'à ce qu'une profondeur définie pour atteindre l'excavation primaire, monter N pannes enveloppantes à l'intérieur de la plage, et mettre sous tension le câble d'ancrage pour le presser contre les N pannes enveloppantes ; (4) excaver le puits de fondation, monter le (N+1)-iéme panne enveloppante, et presser le câble d'ancrage contre le (N+1)-ième panne enveloppante ; (5) achever le montage de toutes les pannes enveloppantes, et couler une plaque inférieure ; (6) retirer les pannes enveloppantes au-dessous de la K-ième plaque supérieure, et construire la K-ième plaque supérieure ; (7) retirer les pannes enveloppantes au-dessous de la (K-1)-ième plaque supérieure, et construire la (K-1)-ième plaque supérieure ; (8) réaliser la construction de plaques supérieures au-dessous de la nième panne enveloppante ; et (9) libérer la tension sur le câble d'ancrage, et construire des plaques supérieures. Selon la présente invention, des parties de support sont remplacées par des pannes enveloppantes, celles-ci servent de parties de transfert de force pour former un pieu vertical précontraint, et sont formées d'une seule pièce avec le pieu vertical, ce qui garantit l'intégrité et la stabilité d'un système de support de fosse de fondation.
本发明公开了地下预应力支护结构的施工方法,步骤:(1)将携带有锚索的支护桩下沉;(2)施工顶部水平支撑;(3)开挖基坑到初次开挖设定深度,安装该范围内的N道围檩,对锚索进行张拉使其抵压在N道围檩上;(4)开挖基坑,安装第N+1道围檩,使锚索抵压在N+1道围檩上;(5)完成所有围檩的安装,浇注底板;(6)拆除第K层顶板以下的围檩,施工第K层顶板;(7)拆除第K-1层顶板以下的围檩,施工第K-1层顶板;(8)完成第N道围檩以下顶板的施工;(9)卸去对锚索的张拉,施工顶板。本申请采用围檩来替代支撑件,并将围檩作为传力件形成预应力支护桩,使围檩与支护桩形成为一个整体,保证了基坑支护系统的整体性和稳定性。
CONSTRUCTION METHOD FOR UNDERGROUND PRESTRESSED SUPPORTING STRUCTURE
Disclosed is a construction method for an underground prestressed supporting structure, comprising the steps of: (1) sinking a soldier pile carrying an anchor cable; (2) constructing a top horizontal support; (3) excavating a foundation pit until a set depth for primary excavation is reached, mounting N enclosing purlins within the range, and tensioning the anchor cable to press same against the N enclosing purlins; (4) excavating the foundation pit, mounting the (N+1)th enclosing purlin, and pressing the anchor cable against the (N+1)th enclosing purlin; (5) completing mounting of all enclosing purlins, and casting a bottom plate; (6) removing the enclosing purlins below the K-th top plate, and constructing the K-th top plate; (7) removing the enclosing purlins below the (K-1)th top plate, and constructing the (K-1)th top plate; (8) completing construction of top plates below the Nth enclosing purlin; and (9) releasing the tensioning on the anchor cable, and constructing top plates. According to the present application, supporting parts are replaced with enclosing purlins, the enclosing purlins serve as force transfer parts to form a prestressed soldier pile, and the enclosing purlins and the soldier pipe are formed as one piece, thereby guaranteeing the integrity and stability of a foundation pit supporting system.
L'invention concerne un procédé de construction pour une structure de support précontrainte souterraine, comprenant les étapes consistant à : (1) enfoncer un pieu vertical portant un câble d'ancrage ; (2) construire un support horizontal supérieur ; (3) excaver une fosse de fondation jusqu'à ce qu'une profondeur définie pour atteindre l'excavation primaire, monter N pannes enveloppantes à l'intérieur de la plage, et mettre sous tension le câble d'ancrage pour le presser contre les N pannes enveloppantes ; (4) excaver le puits de fondation, monter le (N+1)-iéme panne enveloppante, et presser le câble d'ancrage contre le (N+1)-ième panne enveloppante ; (5) achever le montage de toutes les pannes enveloppantes, et couler une plaque inférieure ; (6) retirer les pannes enveloppantes au-dessous de la K-ième plaque supérieure, et construire la K-ième plaque supérieure ; (7) retirer les pannes enveloppantes au-dessous de la (K-1)-ième plaque supérieure, et construire la (K-1)-ième plaque supérieure ; (8) réaliser la construction de plaques supérieures au-dessous de la nième panne enveloppante ; et (9) libérer la tension sur le câble d'ancrage, et construire des plaques supérieures. Selon la présente invention, des parties de support sont remplacées par des pannes enveloppantes, celles-ci servent de parties de transfert de force pour former un pieu vertical précontraint, et sont formées d'une seule pièce avec le pieu vertical, ce qui garantit l'intégrité et la stabilité d'un système de support de fosse de fondation.
本发明公开了地下预应力支护结构的施工方法,步骤:(1)将携带有锚索的支护桩下沉;(2)施工顶部水平支撑;(3)开挖基坑到初次开挖设定深度,安装该范围内的N道围檩,对锚索进行张拉使其抵压在N道围檩上;(4)开挖基坑,安装第N+1道围檩,使锚索抵压在N+1道围檩上;(5)完成所有围檩的安装,浇注底板;(6)拆除第K层顶板以下的围檩,施工第K层顶板;(7)拆除第K-1层顶板以下的围檩,施工第K-1层顶板;(8)完成第N道围檩以下顶板的施工;(9)卸去对锚索的张拉,施工顶板。本申请采用围檩来替代支撑件,并将围檩作为传力件形成预应力支护桩,使围檩与支护桩形成为一个整体,保证了基坑支护系统的整体性和稳定性。
CONSTRUCTION METHOD FOR UNDERGROUND PRESTRESSED SUPPORTING STRUCTURE
PROCÉDÉ DE CONSTRUCTION POUR UNE STRUCTURE DE SUPPORT PRÉCONTRAINTE SOUTERRAINE
一种地下预应力支护结构的施工方法
WANG TAO (author) / LI RENMIN (author) / WANG JIANLAN (author)
2021-10-07
Patent
Electronic Resource
Chinese
IPC:
E02D
FOUNDATIONS
,
Gründungen
Construction method of underground prestressed supporting structure
European Patent Office | 2020
|Prestressed system fabricated underground structure and construction method thereof
European Patent Office | 2021
|Prestressed steel pipe supporting structure and construction method thereof
European Patent Office | 2020
|Prestressed reinforced concrete supporting structure and construction method thereof
European Patent Office | 2024
|Prestressed concrete foundation pit supporting structure and construction method
European Patent Office | 2021
|