HIGH-PRESSURE PRE-FILLED KARST CAVE PILE FOUNDATION CONSTRUCTION METHOD
A high-pressure pre-filled karst cave pile foundation construction method, comprising the following steps: S1, ground drilling: drilling a filling hole (4) and an observation hole (5) on the ground; S2, surveying an internal condition of a karst cave, and determining an internal size of the karst cave; S3, pipe lowering: lowering a filling pipe (8) to the bottom of the karst cave via the filling hole (4), and lowering an observation pipe (6) into the karst cave via the observation hole (5); S4, pre-mixing a filling material (9); S5, filling material (9) backfilling: injecting the filling material (9) into the filling pipe (8), so that the filling material (9) fills the bottom of the karst cave, and continuously raising the height of the filling pipe (8) along with the injection of the filling material (9); and S6, stopping filling, pulling out the filling pipe (8), and waiting for the hardening of the filling material (9). The present construction method is simple and convenient, and may pre-fill a multilayer karst cave and improve a bad geological condition, so as to make the karst cave (2) satisfy a construction requirement of a cast-in-place pile, improve later pile foundation construction efficiency, and reduce construction cost.
L'invention concerne un procédé de construction de fondation sur pieux de caverne karstique pré-remplie à haute pression, comprenant les étapes suivantes : S1, forage au sol : réalisation du forage d'un trou de remplissage (4) et d'un trou d'observation (5) dans le sol ; S2, arpentage de l'état interne d'une caverne karstique, et détermination de la taille interne de celle-ci ; S3, abaissement de tuyau : abaissement d'un tuyau de remplissage (8) vers le fond de la caverne karstique par l'intermédiaire du trou de remplissage (4), et abaissement d'un tuyau d'observation (6) dans la caverne karstique par l'intermédiaire du trou d'observation (5) ; S4, pré-mélange d'un matériau de remplissage (9) ; S5, remplissage du matériau de remplissage (9) : injection du matériau de remplissage (9) dans le tuyau de remplissage (8), de telle sorte que le matériau de remplissage (9) remplit le fond de la cavité karstique, et élévation en continu de la hauteur du tuyau de remplissage (8) conjointement avec l'injection du matériau de remplissage (9) ; et S6, arrêt du remplissage, retrait du tuyau de remplissage (8), et attente du durcissement du matériau de remplissage (9). Le présent procédé de construction est simple et pratique, et peut pré-remplir une caverne karstique multicouche et améliorer une mauvaise condition géologique, de façon à amener la caverne karstique (2) à satisfaire une exigence de construction d'un pieu coulé sur place, à améliorer l'efficacité de construction de fondation sur pieux ultérieure, et à réduire le coût de construction.
一种高压预填充溶洞桩基施工方法,包括如下步骤:S1:地面钻孔:在地面钻取填充孔(4)和观察孔(5);S2:勘察溶洞内部情况,确定溶洞内部大小;S3:下放管道:填充管(8)通过填充孔(4)下放到溶洞底部,观测管(6)通过观察孔(5)下放到溶洞中;S4:预拌填充料(9);S5:回填填充料(9):将填充料(9)注入填充管(8)中,填充料(9)填入溶洞底部,且随着填充料(9)的注入,不断抬高填充管(8)的高度;S6:停止填充,拔出填充管(8),静待填充料(9)硬化。本施工方法简单方便,能对多层溶洞进行预填充处理,改善不良地质条件,使溶洞(2)满足灌注桩施工要求,提高后期桩基础施工效率,降低施工成本。
HIGH-PRESSURE PRE-FILLED KARST CAVE PILE FOUNDATION CONSTRUCTION METHOD
A high-pressure pre-filled karst cave pile foundation construction method, comprising the following steps: S1, ground drilling: drilling a filling hole (4) and an observation hole (5) on the ground; S2, surveying an internal condition of a karst cave, and determining an internal size of the karst cave; S3, pipe lowering: lowering a filling pipe (8) to the bottom of the karst cave via the filling hole (4), and lowering an observation pipe (6) into the karst cave via the observation hole (5); S4, pre-mixing a filling material (9); S5, filling material (9) backfilling: injecting the filling material (9) into the filling pipe (8), so that the filling material (9) fills the bottom of the karst cave, and continuously raising the height of the filling pipe (8) along with the injection of the filling material (9); and S6, stopping filling, pulling out the filling pipe (8), and waiting for the hardening of the filling material (9). The present construction method is simple and convenient, and may pre-fill a multilayer karst cave and improve a bad geological condition, so as to make the karst cave (2) satisfy a construction requirement of a cast-in-place pile, improve later pile foundation construction efficiency, and reduce construction cost.
L'invention concerne un procédé de construction de fondation sur pieux de caverne karstique pré-remplie à haute pression, comprenant les étapes suivantes : S1, forage au sol : réalisation du forage d'un trou de remplissage (4) et d'un trou d'observation (5) dans le sol ; S2, arpentage de l'état interne d'une caverne karstique, et détermination de la taille interne de celle-ci ; S3, abaissement de tuyau : abaissement d'un tuyau de remplissage (8) vers le fond de la caverne karstique par l'intermédiaire du trou de remplissage (4), et abaissement d'un tuyau d'observation (6) dans la caverne karstique par l'intermédiaire du trou d'observation (5) ; S4, pré-mélange d'un matériau de remplissage (9) ; S5, remplissage du matériau de remplissage (9) : injection du matériau de remplissage (9) dans le tuyau de remplissage (8), de telle sorte que le matériau de remplissage (9) remplit le fond de la cavité karstique, et élévation en continu de la hauteur du tuyau de remplissage (8) conjointement avec l'injection du matériau de remplissage (9) ; et S6, arrêt du remplissage, retrait du tuyau de remplissage (8), et attente du durcissement du matériau de remplissage (9). Le présent procédé de construction est simple et pratique, et peut pré-remplir une caverne karstique multicouche et améliorer une mauvaise condition géologique, de façon à amener la caverne karstique (2) à satisfaire une exigence de construction d'un pieu coulé sur place, à améliorer l'efficacité de construction de fondation sur pieux ultérieure, et à réduire le coût de construction.
一种高压预填充溶洞桩基施工方法,包括如下步骤:S1:地面钻孔:在地面钻取填充孔(4)和观察孔(5);S2:勘察溶洞内部情况,确定溶洞内部大小;S3:下放管道:填充管(8)通过填充孔(4)下放到溶洞底部,观测管(6)通过观察孔(5)下放到溶洞中;S4:预拌填充料(9);S5:回填填充料(9):将填充料(9)注入填充管(8)中,填充料(9)填入溶洞底部,且随着填充料(9)的注入,不断抬高填充管(8)的高度;S6:停止填充,拔出填充管(8),静待填充料(9)硬化。本施工方法简单方便,能对多层溶洞进行预填充处理,改善不良地质条件,使溶洞(2)满足灌注桩施工要求,提高后期桩基础施工效率,降低施工成本。
HIGH-PRESSURE PRE-FILLED KARST CAVE PILE FOUNDATION CONSTRUCTION METHOD
PROCÉDÉ DE CONSTRUCTION DE FONDATION SUR PIEUX DE CAVERNE KARSTIQUE PRÉ-REMPLIE À HAUTE PRESSION
一种高压预填充溶洞桩基施工方法
LIU YONGFENG (author) / RONG JINGSONG (author) / XIAO CHENGHUI (author) / WANG YUANZHE (author) / ZENG FEI (author) / HUANG GUOZHONG (author) / SHAN LIANG (author) / ZHOU HANBIN (author)
2023-09-28
Patent
Electronic Resource
Chinese
IPC:
E02D
FOUNDATIONS
,
Gründungen
High-pressure pre-filling karst cave pile foundation construction method
European Patent Office | 2022
|Karst cave pile foundation construction method and device
European Patent Office | 2023
|Stacked karst cave stratum pile foundation construction method
European Patent Office | 2022
|Construction method of bridge pile foundation of flow plastic semi-filled karst cave
European Patent Office | 2023
|European Patent Office | 2021
|