A platform for research: civil engineering, architecture and urbanism
SWING METHOD FOR DUAL-DECK CURVED GIRDER BRIDGE
The present invention relates to the technical field of bridge construction, and provides a swing method for a dual-deck curved girder bridge. The swing method for a dual-deck curved girder bridge comprises: S1: removing construction loads from a left bridge deck and a right bridge deck, performing a counterweight weighing test, and adjusting the structural center of gravity; S2: synchronously performing trial swing operations on a left bridge and a right bridge, verifying a coefficient of friction resistance and a traction force, and checking the balance stability of swing; S3: synchronously performing formal swing operations on the left bridge and the right bridge, and in the last stage of swing, implementing inching to ensure that swing is performed in place accurately; and S4: after swing is performed in place, temporarily supporting, on temporary cushions for receiving pier tops, cantilevers at both ends of each of the left bridge and the right bridge, and temporarily locking steel girders. In the present invention, the left and right bridges swing by different angles, and during trail swing, the angle of swing of the left bridge is 1° greater than that of the right bridge to ensure that the angles of swing of the left and right bridges are consistent during subsequent swing, thereby facilitating operations and observations during subsequent swing, and achieving relatively equidistant and synchronous swing operations.
La présente invention se rapporte au domaine technique de la construction de pont, et concerne un procédé d'oscillation pour un pont à poutres courbé à double tablier. Le procédé d'oscillation pour un pont à poutres courbé à double tablier consiste à : S1 : retirer des charges de construction d'un tablier de pont gauche et d'un tablier de pont droit, effectuer un test de pesée de contrepoids, et ajuster le centre de gravité structural ; S2 : mettre en œuvre de manière synchrone des opérations d'oscillation d'essai sur un pont gauche et un pont droit, vérifier un coefficient de résistance au frottement et une force de traction, et contrôler de la stabilité d'équilibre de l'oscillation ; S3 : effectuer de manière synchrone des opérations d'oscillation formelles sur le pont gauche et le pont droit, et dans la dernière étape d'oscillation, effectuer un réglage progressif pour assurer qu'une oscillation est effectuée en place avec précision ; et S4 : après qu'une oscillation s'effectue en place, supporter temporairement, sur des amortisseurs temporaires destinés à recevoir des sommets de pile, des porte-à-faux aux deux extrémités de chacun du pont gauche et du pont droit, et verrouiller temporairement des poutres en acier. Dans la présente invention, les ponts gauche et droit oscillent selon différents angles, et pendant l'oscillation de la piste, l'angle d'oscillation du pont gauche est supérieur de 1° à celui du pont droit pour s'assurer que les angles d'oscillation des ponts gauche et droit sont compatibles pendant l'oscillation suivante, ce qui facilite les opérations et les observations pendant l'oscillation suivante, et permet d'effectuer des opérations d'oscillation relativement équidistantes et synchrones.
本发明提供了一种双幅曲线梁桥的转体方法,涉及桥梁施工技术领域,双幅曲线梁桥的转体方法包括:S1:清除左幅桥面与右幅桥面的施工荷载,进行称配重试验,调整结构重心;S2:对左幅桥与右幅桥同步进行试转体操作,校核摩阻系数、牵引力,检查转体的平衡稳定性;S3:对左幅桥与右幅桥同步进行正式转体操作,转体最后阶段采用点动,确保转体准确就位;S4:转体就位后,左幅桥与右幅桥两端悬臂临时支撑于接收墩顶的临时抄垫上,并临时锁定钢梁。本发明中左右幅桥转体的角度不同,试转左幅比右幅多转1°是为了保证后续转体时左右幅转体角度一致,方便后续转体的的操作和观测,实现相对等间距与等同步的转体操作。
SWING METHOD FOR DUAL-DECK CURVED GIRDER BRIDGE
The present invention relates to the technical field of bridge construction, and provides a swing method for a dual-deck curved girder bridge. The swing method for a dual-deck curved girder bridge comprises: S1: removing construction loads from a left bridge deck and a right bridge deck, performing a counterweight weighing test, and adjusting the structural center of gravity; S2: synchronously performing trial swing operations on a left bridge and a right bridge, verifying a coefficient of friction resistance and a traction force, and checking the balance stability of swing; S3: synchronously performing formal swing operations on the left bridge and the right bridge, and in the last stage of swing, implementing inching to ensure that swing is performed in place accurately; and S4: after swing is performed in place, temporarily supporting, on temporary cushions for receiving pier tops, cantilevers at both ends of each of the left bridge and the right bridge, and temporarily locking steel girders. In the present invention, the left and right bridges swing by different angles, and during trail swing, the angle of swing of the left bridge is 1° greater than that of the right bridge to ensure that the angles of swing of the left and right bridges are consistent during subsequent swing, thereby facilitating operations and observations during subsequent swing, and achieving relatively equidistant and synchronous swing operations.
La présente invention se rapporte au domaine technique de la construction de pont, et concerne un procédé d'oscillation pour un pont à poutres courbé à double tablier. Le procédé d'oscillation pour un pont à poutres courbé à double tablier consiste à : S1 : retirer des charges de construction d'un tablier de pont gauche et d'un tablier de pont droit, effectuer un test de pesée de contrepoids, et ajuster le centre de gravité structural ; S2 : mettre en œuvre de manière synchrone des opérations d'oscillation d'essai sur un pont gauche et un pont droit, vérifier un coefficient de résistance au frottement et une force de traction, et contrôler de la stabilité d'équilibre de l'oscillation ; S3 : effectuer de manière synchrone des opérations d'oscillation formelles sur le pont gauche et le pont droit, et dans la dernière étape d'oscillation, effectuer un réglage progressif pour assurer qu'une oscillation est effectuée en place avec précision ; et S4 : après qu'une oscillation s'effectue en place, supporter temporairement, sur des amortisseurs temporaires destinés à recevoir des sommets de pile, des porte-à-faux aux deux extrémités de chacun du pont gauche et du pont droit, et verrouiller temporairement des poutres en acier. Dans la présente invention, les ponts gauche et droit oscillent selon différents angles, et pendant l'oscillation de la piste, l'angle d'oscillation du pont gauche est supérieur de 1° à celui du pont droit pour s'assurer que les angles d'oscillation des ponts gauche et droit sont compatibles pendant l'oscillation suivante, ce qui facilite les opérations et les observations pendant l'oscillation suivante, et permet d'effectuer des opérations d'oscillation relativement équidistantes et synchrones.
本发明提供了一种双幅曲线梁桥的转体方法,涉及桥梁施工技术领域,双幅曲线梁桥的转体方法包括:S1:清除左幅桥面与右幅桥面的施工荷载,进行称配重试验,调整结构重心;S2:对左幅桥与右幅桥同步进行试转体操作,校核摩阻系数、牵引力,检查转体的平衡稳定性;S3:对左幅桥与右幅桥同步进行正式转体操作,转体最后阶段采用点动,确保转体准确就位;S4:转体就位后,左幅桥与右幅桥两端悬臂临时支撑于接收墩顶的临时抄垫上,并临时锁定钢梁。本发明中左右幅桥转体的角度不同,试转左幅比右幅多转1°是为了保证后续转体时左右幅转体角度一致,方便后续转体的的操作和观测,实现相对等间距与等同步的转体操作。
SWING METHOD FOR DUAL-DECK CURVED GIRDER BRIDGE
PROCÉDÉ D'OSCILLATION POUR PONT À POUTRES COURBÉ À DOUBLE TABLIER
一种双幅曲线梁桥的转体方法
LI TONG (author) / LIANG HUI (author) / HUANG XINGYU (author) / ZHU DONGMING (author) / YU WEIJIE (author) / LONG YUYI (author) / ZHANG YANHUI (author) / XIA CHAOJUAN (author) / LI FENG (author) / SU YAN (author)
2024-07-18
Patent
Electronic Resource
Chinese
IPC:
E01D
BRIDGES
,
Brücken
Box girder on single columns supports curved bridge deck
Engineering Index Backfile | 1949
|Box girder on single columns supports curved bridge deck
Engineering Index Backfile | 1948
|METHOD FOR ERECTING LARGE-RADIAN CURVED STEEL BOX GIRDER BRIDGE DECK
European Patent Office | 2022
|Bridge Deck Design Considering Girder Deflections
British Library Conference Proceedings | 1998
|PRR installs all-welded deck-girder bridge
Engineering Index Backfile | 1964