CONSTRUCTION METHOD FOR IN-WATER PILE SINKING BASED ON MOBILE PILING PLATFORM
Disclosed in the present invention is a construction method for in-water pile sinking based on a mobile piling platform, which comprises the following steps: S1, constructing an auxiliary platform, assembling a mobile piling platform on the auxiliary platform, arranging a rail pile group on one side of the auxiliary platform, mounting a pile sending rail on the rail pile group, and mounting a pile sendind trolley on the pile sending rail; S2, sending, by the pile sending trolley, a single steel pipe pile loaded therein to a pile hoisting range, hoisting the steel pipe pile, and placing the steel pipe pile into a corresponding pile holding device for pile sinking, wherein after the steel pipe pile is hoisted, the pile sending trolley returns to a starting point to continue next pile sending operation; S3, repeating step S2 until the mobile piling platform completes construction of all the steel pipe piles in this span section, and extending the pile sending rail; S4, driving the mobile piling platform to move forwards by one span section, and repeating steps S2-S3 to carry out pile sinking construction of steel pipe piles in the next span section; and S5, repeating step S4 until the construction of all the steel pipe piles is completed. The present invention has the beneficial effect that constructing the pile sending rail depending on the steel pipe piles facilitates a conveying rail.
La présente invention concerne un procédé de construction pour un enfoncement de pieu dans l'eau sur la base d'une plateforme d'empilement mobile. Ledit procédé comprend les étapes suivantes : S1, la construction d'une plateforme auxiliaire, l'assemblage d'une plateforme d'empilement mobile sur la plateforme auxiliaire, l'agencement d'un groupe de pieux de rail sur un côté de la plateforme auxiliaire, le montage d'un rail d'envoi de pieu sur le groupe de pieux de rail, et le montage d'un chariot d'envoi de pieu sur le rail d'envoi de pieu ; S2, l'envoi, par le chariot d'envoi de pieu, d'un pieu tubulaire en acier unique chargé dans celui-ci à une plage de levage de pieu, le levage du pieu tubulaire en acier, et le placement du pieu tubulaire en acier dans un dispositif de maintien de pieu correspondant pour un enfoncement de pieu, après le levage du pieu tubulaire en acier, le chariot d'envoi de pieu revenant à un point de départ pour continuer l'opération d'envoi de pieu suivant ; S3, la répétition de l'étape S2 jusqu'à ce que la plateforme d'empilement mobile achève la construction de tous les pieux de tuyau en acier dans cette section d'envergure, et l'extension du rail d'envoi de pieu ; S4, l'entraînement de la plateforme d'empilement mobile à se déplacer vers l'avant par une section d'envergure, et la répétition des étapes S2-S3 pour réaliser une construction d'enfoncement de pieu de pieux de tuyau en acier dans la section d'envergure suivante ; et S5, la répétition de l'étape S4 jusqu'à ce que la construction de tous les pieux de tuyau en acier soit achevée. La présente invention présente l'effet bénéfique que la construction du rail d'envoi de pieu en fonction des pieux de tuyau en acier facilite un rail de transport.
本发明公开了一种基于移动打桩平台进行水上沉桩的施工方法,包括以下步骤:S1、构建辅助平台,在辅助平台上拼装移动打桩平台,在辅助平台一侧设置轨道桩群,在轨道桩群上安装送桩轨道,在送桩轨道上安装送桩小车;S2、通过送桩小车载单根钢管桩运送至吊桩范围,起吊钢管桩,并送入对应的抱桩器中沉桩,其中,钢管桩起吊完成后,送桩小车返回起点继续下一根送桩作业;S3、重复S2至移动式打桩平台在该跨的钢管桩全部施工完成,延伸设置送桩轨道;S4、驱动移动式打桩平台前进1跨,并重复S2-S3进行下一跨钢管桩的沉桩施工;S5、重复步骤S4直至所有钢管桩施工完成。本发明具有依靠钢管桩构建送桩轨道便利输送轨道的有益效果。
CONSTRUCTION METHOD FOR IN-WATER PILE SINKING BASED ON MOBILE PILING PLATFORM
Disclosed in the present invention is a construction method for in-water pile sinking based on a mobile piling platform, which comprises the following steps: S1, constructing an auxiliary platform, assembling a mobile piling platform on the auxiliary platform, arranging a rail pile group on one side of the auxiliary platform, mounting a pile sending rail on the rail pile group, and mounting a pile sendind trolley on the pile sending rail; S2, sending, by the pile sending trolley, a single steel pipe pile loaded therein to a pile hoisting range, hoisting the steel pipe pile, and placing the steel pipe pile into a corresponding pile holding device for pile sinking, wherein after the steel pipe pile is hoisted, the pile sending trolley returns to a starting point to continue next pile sending operation; S3, repeating step S2 until the mobile piling platform completes construction of all the steel pipe piles in this span section, and extending the pile sending rail; S4, driving the mobile piling platform to move forwards by one span section, and repeating steps S2-S3 to carry out pile sinking construction of steel pipe piles in the next span section; and S5, repeating step S4 until the construction of all the steel pipe piles is completed. The present invention has the beneficial effect that constructing the pile sending rail depending on the steel pipe piles facilitates a conveying rail.
La présente invention concerne un procédé de construction pour un enfoncement de pieu dans l'eau sur la base d'une plateforme d'empilement mobile. Ledit procédé comprend les étapes suivantes : S1, la construction d'une plateforme auxiliaire, l'assemblage d'une plateforme d'empilement mobile sur la plateforme auxiliaire, l'agencement d'un groupe de pieux de rail sur un côté de la plateforme auxiliaire, le montage d'un rail d'envoi de pieu sur le groupe de pieux de rail, et le montage d'un chariot d'envoi de pieu sur le rail d'envoi de pieu ; S2, l'envoi, par le chariot d'envoi de pieu, d'un pieu tubulaire en acier unique chargé dans celui-ci à une plage de levage de pieu, le levage du pieu tubulaire en acier, et le placement du pieu tubulaire en acier dans un dispositif de maintien de pieu correspondant pour un enfoncement de pieu, après le levage du pieu tubulaire en acier, le chariot d'envoi de pieu revenant à un point de départ pour continuer l'opération d'envoi de pieu suivant ; S3, la répétition de l'étape S2 jusqu'à ce que la plateforme d'empilement mobile achève la construction de tous les pieux de tuyau en acier dans cette section d'envergure, et l'extension du rail d'envoi de pieu ; S4, l'entraînement de la plateforme d'empilement mobile à se déplacer vers l'avant par une section d'envergure, et la répétition des étapes S2-S3 pour réaliser une construction d'enfoncement de pieu de pieux de tuyau en acier dans la section d'envergure suivante ; et S5, la répétition de l'étape S4 jusqu'à ce que la construction de tous les pieux de tuyau en acier soit achevée. La présente invention présente l'effet bénéfique que la construction du rail d'envoi de pieu en fonction des pieux de tuyau en acier facilite un rail de transport.
本发明公开了一种基于移动打桩平台进行水上沉桩的施工方法,包括以下步骤:S1、构建辅助平台,在辅助平台上拼装移动打桩平台,在辅助平台一侧设置轨道桩群,在轨道桩群上安装送桩轨道,在送桩轨道上安装送桩小车;S2、通过送桩小车载单根钢管桩运送至吊桩范围,起吊钢管桩,并送入对应的抱桩器中沉桩,其中,钢管桩起吊完成后,送桩小车返回起点继续下一根送桩作业;S3、重复S2至移动式打桩平台在该跨的钢管桩全部施工完成,延伸设置送桩轨道;S4、驱动移动式打桩平台前进1跨,并重复S2-S3进行下一跨钢管桩的沉桩施工;S5、重复步骤S4直至所有钢管桩施工完成。本发明具有依靠钢管桩构建送桩轨道便利输送轨道的有益效果。
CONSTRUCTION METHOD FOR IN-WATER PILE SINKING BASED ON MOBILE PILING PLATFORM
PROCÉDÉ DE CONSTRUCTION POUR UN ENFONCEMENT DE PIEU DANS L'EAU SUR LA BASE D'UNE PLATEFORME D'EMPILEMENT MOBILE
基于移动打桩平台进行水上沉桩的施工方法
BAI YINZHAN (author)
2024-12-05
Patent
Electronic Resource
Chinese
Pipe end inner hammer piling device, assembling method and pile sinking construction method
European Patent Office | 2024
|Construction method for water pile sinking based on movable pile driving platform
European Patent Office | 2023
|European Patent Office | 2023
|Multifunctional piling machine and row inclined pile piling construction method
European Patent Office | 2023
|