The invention relates to the field of building construction, and particularly relates to a beam plate support construction method. The beam plate support construction method comprises the steps that abeam plate mounting area is equally divided into a plurality of areas; the number of portal scaffolds is determined according to the corresponding equally-divided area areas; a plurality of portal scaffolds are spliced into a whole corresponding to the equally-divided area areas; the erected portal scaffolds are integrally placed on one side of a construction area, and beam plate construction isstarted from one side of the construction area; and the portal scaffolds are integrally moved to the other side of the construction area section by section, and beam plate construction is conducted onthe construction area section by section till beam plate mounting of the whole construction area is completed. The beam plate support construction method is high in practicability and flexibility, the construction efficiency can be integrally improved, and the construction period is shortened.
本发明涉及建筑施工领域,尤其是一种梁板支撑施工方法,将梁板安装区域等分成多个区域;对应等分的区域面积确定门式脚手架个数;将多个门式脚手架对应等分区域面积拼接成一个整体;搭设好的门式脚手架整体置于施工区域的一侧,由施工区域的一侧开始进行梁板施工;将门式脚手架整体逐段向施工区域的另一侧移动,对施工区域逐段进行梁板施工,直到整个施工区域梁板安装完成为止。本发明实用灵活性高,能够整体提高施工效率,缩短施工工期。
Beam plate support construction method
The invention relates to the field of building construction, and particularly relates to a beam plate support construction method. The beam plate support construction method comprises the steps that abeam plate mounting area is equally divided into a plurality of areas; the number of portal scaffolds is determined according to the corresponding equally-divided area areas; a plurality of portal scaffolds are spliced into a whole corresponding to the equally-divided area areas; the erected portal scaffolds are integrally placed on one side of a construction area, and beam plate construction isstarted from one side of the construction area; and the portal scaffolds are integrally moved to the other side of the construction area section by section, and beam plate construction is conducted onthe construction area section by section till beam plate mounting of the whole construction area is completed. The beam plate support construction method is high in practicability and flexibility, the construction efficiency can be integrally improved, and the construction period is shortened.
本发明涉及建筑施工领域,尤其是一种梁板支撑施工方法,将梁板安装区域等分成多个区域;对应等分的区域面积确定门式脚手架个数;将多个门式脚手架对应等分区域面积拼接成一个整体;搭设好的门式脚手架整体置于施工区域的一侧,由施工区域的一侧开始进行梁板施工;将门式脚手架整体逐段向施工区域的另一侧移动,对施工区域逐段进行梁板施工,直到整个施工区域梁板安装完成为止。本发明实用灵活性高,能够整体提高施工效率,缩短施工工期。
Beam plate support construction method
梁板支撑施工方法
LI ZHEN (Autor:in) / SUN HAI (Autor:in) / WANG ZHENBO (Autor:in) / WANG GENG (Autor:in)
09.03.2021
Patent
Elektronische Ressource
Chinesisch
IPC:
E04G
SCAFFOLDING
,
Baugerüste
BEAM BRIDGE HAVING BEAM SUPPORT PLATE AND CONSTRUCTION METHOD THEREFOR
Europäisches Patentamt | 2018
|Europäisches Patentamt | 2024
|Floor support plate support construction method and floor support plate support structure
Europäisches Patentamt | 2024
|Prefabricated hanging plate device for crown beam steel support and construction method
Europäisches Patentamt | 2023
|