Defect repairing method for cast-in-place pile
The invention provides a defect repairing method for a cast-in-place pile, and relates to the field of pile foundation repairing. The repairing method comprises the steps that 1, the position and sizeof a pile body defect are determined through a sound wave transmission method; 2, a drill bit is used for continuously coring around the center of the cast-in-place pile to form an annular separationgroove, a concrete core column is broken and hoisted out, and a central vertical shaft is constructed in the cast-in-place pile; 3, the step 2 is repeated, and the depth of the central vertical shaftis increased till the bottom of the central vertical shaft reaches the position below the pile body defect; 4, a constructor descends into a well to chisel away and clean the pile body defect, and drilling slag and concrete chippings on the well wall are flushed away; 5, accumulated water and sediments in the central vertical shaft are discharged, and concrete is poured into the central verticalshaft and vibrated to be compact; and 6, after the strength of the concrete meets the requirement, the cast-in-place pile is rechecked and detected, and it is guaranteed that the quality of the cast-in-place pile meets the standard. Construction personnel can go deep into the cast-in-place pile to conduct visual removal operation, and the repairing effect is better.
本发明提供了一种灌注桩的缺陷修复方法,涉及桩基修复领域。该修复方法包括:步骤一、采用声波透射法确定桩身缺陷的位置和大小;步骤二、利用钻头围绕灌注桩的中心进行连续取芯形成环形分隔槽,折断混凝土芯柱并吊运出去,在灌注桩的内部构造出中心竖井;步骤三、重复步骤二,加大中心竖井的深度,直至中心竖井的底部到达桩身缺陷以下;步骤四、由施工人员下井凿除并清理桩身缺陷,冲洗去除井壁的钻渣和砼屑;步骤五、排出中心竖井中的积水和沉渣,向中心竖井中灌注混凝土并振捣密实;步骤六、待混凝土强度达到要求后,对灌注桩进行复查检测,确保灌注桩的质量符合标准。施工人员可深入灌注桩的内部进行可视化清除操作,修复效果更好。
Defect repairing method for cast-in-place pile
The invention provides a defect repairing method for a cast-in-place pile, and relates to the field of pile foundation repairing. The repairing method comprises the steps that 1, the position and sizeof a pile body defect are determined through a sound wave transmission method; 2, a drill bit is used for continuously coring around the center of the cast-in-place pile to form an annular separationgroove, a concrete core column is broken and hoisted out, and a central vertical shaft is constructed in the cast-in-place pile; 3, the step 2 is repeated, and the depth of the central vertical shaftis increased till the bottom of the central vertical shaft reaches the position below the pile body defect; 4, a constructor descends into a well to chisel away and clean the pile body defect, and drilling slag and concrete chippings on the well wall are flushed away; 5, accumulated water and sediments in the central vertical shaft are discharged, and concrete is poured into the central verticalshaft and vibrated to be compact; and 6, after the strength of the concrete meets the requirement, the cast-in-place pile is rechecked and detected, and it is guaranteed that the quality of the cast-in-place pile meets the standard. Construction personnel can go deep into the cast-in-place pile to conduct visual removal operation, and the repairing effect is better.
本发明提供了一种灌注桩的缺陷修复方法,涉及桩基修复领域。该修复方法包括:步骤一、采用声波透射法确定桩身缺陷的位置和大小;步骤二、利用钻头围绕灌注桩的中心进行连续取芯形成环形分隔槽,折断混凝土芯柱并吊运出去,在灌注桩的内部构造出中心竖井;步骤三、重复步骤二,加大中心竖井的深度,直至中心竖井的底部到达桩身缺陷以下;步骤四、由施工人员下井凿除并清理桩身缺陷,冲洗去除井壁的钻渣和砼屑;步骤五、排出中心竖井中的积水和沉渣,向中心竖井中灌注混凝土并振捣密实;步骤六、待混凝土强度达到要求后,对灌注桩进行复查检测,确保灌注桩的质量符合标准。施工人员可深入灌注桩的内部进行可视化清除操作,修复效果更好。
Defect repairing method for cast-in-place pile
一种灌注桩的缺陷修复方法
YANG YONG (Autor:in) / ZHAN YUANLIN (Autor:in) / RONG GUOCHENG (Autor:in) / XIE CHAOJUN (Autor:in) / PENG KUN (Autor:in) / LIU YONGJIE (Autor:in) / LIANG SHIKAI (Autor:in) / LIU CHENGHONG (Autor:in) / LENG LIN (Autor:in)
12.03.2021
Patent
Elektronische Ressource
Chinesisch
IPC:
E02D
FOUNDATIONS
,
Gründungen
Cast-in-place pile defect detecting and repairing method for construction engineering
Europäisches Patentamt | 2020
|Turnover type cast-in-place pile head defect repairing mold structure and construction method
Europäisches Patentamt | 2023
|Europäisches Patentamt | 2021
|Method and system for repairing defective cast-in-place pile
Europäisches Patentamt | 2020
|