Method for controlling perpendicularity of pile body
A method for controlling the perpendicularity of a pile body is characterized by comprising the following steps that a, the pile body (1) is hoisted through a crane (4), and the pile body is aligned with a pile center control point; b, correcting the perpendicularity of the pile body by using a first total station (2); c, correcting the perpendicularity of the pile body by using a second total station (3); d, the first total station and the second total station are used for conducting perpendicularity correction on the pile body at the same time; and e, the pile body is conveyed downwards, the pile top is conveyed to the designed elevation, and the first total station (2) and the second total station (3) are arranged to form 90 degrees relative to the pile body (1). The method for controlling the perpendicularity of the pile body has the advantages that through application of the two total stations, the perpendicularity of the pile body is remarkably guaranteed, deviation of the pile body is effectively reduced, the construction quality of pile foundation engineering is improved, the stability and safety of a pile foundation are enhanced, operation is convenient and fast, and the construction difficulty and cost are reduced.
一种控制桩身垂直度的方法,其特征在于包括以下步骤:a、用吊机(4)将桩身(1)吊起,并将桩身对准桩心控制点;b、用第一全站仪(2)对桩身进行垂直度矫正;c、用第二全站仪(3)对桩身进行垂直度矫正;d、用第一全站仪和第二全站仪对桩身同时进行垂直度矫正;e、将桩身向下送桩,使桩顶送至设计标高,其中:所述第一全站仪(2)与第二全站仪(3)之间对于桩身(1)成90度设置。本发明的控制桩身垂直度的方法具有通过两台全站仪的应用,显著保障了桩身的垂直度,有效减小桩身的偏差,提高桩基工程的施工质量,增强桩基的稳定性和安全性,操作便捷快速,降低施工难度和成本的优点。
Method for controlling perpendicularity of pile body
A method for controlling the perpendicularity of a pile body is characterized by comprising the following steps that a, the pile body (1) is hoisted through a crane (4), and the pile body is aligned with a pile center control point; b, correcting the perpendicularity of the pile body by using a first total station (2); c, correcting the perpendicularity of the pile body by using a second total station (3); d, the first total station and the second total station are used for conducting perpendicularity correction on the pile body at the same time; and e, the pile body is conveyed downwards, the pile top is conveyed to the designed elevation, and the first total station (2) and the second total station (3) are arranged to form 90 degrees relative to the pile body (1). The method for controlling the perpendicularity of the pile body has the advantages that through application of the two total stations, the perpendicularity of the pile body is remarkably guaranteed, deviation of the pile body is effectively reduced, the construction quality of pile foundation engineering is improved, the stability and safety of a pile foundation are enhanced, operation is convenient and fast, and the construction difficulty and cost are reduced.
一种控制桩身垂直度的方法,其特征在于包括以下步骤:a、用吊机(4)将桩身(1)吊起,并将桩身对准桩心控制点;b、用第一全站仪(2)对桩身进行垂直度矫正;c、用第二全站仪(3)对桩身进行垂直度矫正;d、用第一全站仪和第二全站仪对桩身同时进行垂直度矫正;e、将桩身向下送桩,使桩顶送至设计标高,其中:所述第一全站仪(2)与第二全站仪(3)之间对于桩身(1)成90度设置。本发明的控制桩身垂直度的方法具有通过两台全站仪的应用,显著保障了桩身的垂直度,有效减小桩身的偏差,提高桩基工程的施工质量,增强桩基的稳定性和安全性,操作便捷快速,降低施工难度和成本的优点。
Method for controlling perpendicularity of pile body
一种控制桩身垂直度的方法
ZHANG HONGKUN (Autor:in) / WANG YUE (Autor:in) / ZHAO YUNFEI (Autor:in) / YAO PEILONG (Autor:in) / LI CHAO (Autor:in)
03.09.2024
Patent
Elektronische Ressource
Chinesisch
IPC:
E02D
FOUNDATIONS
,
Gründungen
Method for controlling perpendicularity of cement mixing pile body
Europäisches Patentamt | 2020
|Europäisches Patentamt | 2015
|Europäisches Patentamt | 2021
|Pile body perpendicularity and pile length optical monitoring method and device
Europäisches Patentamt | 2020
|