Hundred-meter-high barrel iron chimney steel frame integral hoisting device and process
The invention discloses a hundred-meter-high barrel iron chimney steel frame integral hoisting device and process, and belongs to the field of building installation. The hundred-meter-high barrel ironchimney steel frame integral hoisting device comprises foundation piles, a foundation plate, foundation piers, first part steel frames, second part steel frames and third part steel frames, wherein the foundation piles are driven to the bottom of a foundation, the foundation plate is laid on the foundation piles, the foundation piers are arranged on the foundation plate, the first part steel frames are installed on the foundation piers, the second part steel frames are fixedly installed at the tops of the first part steel frames, and the third part steel frames are fixedly installed at the tops of the second part steel frames. According to the hundred-meter-high barrel iron chimney steel frame integral hoisting device and process, a hundred-meter-high barrel iron chimney and an external steel truss hoisting construction process can be applied to installation and construction of large high-rise steel structures, the process is simple, safe and reliable, the construction cost is saved,all operation of bottom hoist lifting is located on the ground, installation and maintenance are convenient, and the operability is higher and safer in case of emergencies.
本发明公开了一种百米高筒体铁质烟囱钢架整体吊装装置及其工艺,属于建筑安装领域,包括地基桩、地基板、基墩、第一部分钢架、第二部分钢架和第三部分钢架,所述地基桩打地基底部,所述地基板铺设在若干根地基桩上,所述基墩设置在地基板上,所述第一部分钢架安装在基墩上,所述第二部分钢架固定安装在第一部分钢架的顶部,所述第三部分钢架固定安装在第二部分钢架的顶部。本发明的百米烟囱及外部钢制桁架吊装施工工艺可以运用在大型高耸钢结构安装施工中,工艺简单,安全可靠,节约施工成本,底部葫芦提升全部操作位于地上,方便安装与维护,面对突发情况操作性更高,更加安全。
Hundred-meter-high barrel iron chimney steel frame integral hoisting device and process
The invention discloses a hundred-meter-high barrel iron chimney steel frame integral hoisting device and process, and belongs to the field of building installation. The hundred-meter-high barrel ironchimney steel frame integral hoisting device comprises foundation piles, a foundation plate, foundation piers, first part steel frames, second part steel frames and third part steel frames, wherein the foundation piles are driven to the bottom of a foundation, the foundation plate is laid on the foundation piles, the foundation piers are arranged on the foundation plate, the first part steel frames are installed on the foundation piers, the second part steel frames are fixedly installed at the tops of the first part steel frames, and the third part steel frames are fixedly installed at the tops of the second part steel frames. According to the hundred-meter-high barrel iron chimney steel frame integral hoisting device and process, a hundred-meter-high barrel iron chimney and an external steel truss hoisting construction process can be applied to installation and construction of large high-rise steel structures, the process is simple, safe and reliable, the construction cost is saved,all operation of bottom hoist lifting is located on the ground, installation and maintenance are convenient, and the operability is higher and safer in case of emergencies.
本发明公开了一种百米高筒体铁质烟囱钢架整体吊装装置及其工艺,属于建筑安装领域,包括地基桩、地基板、基墩、第一部分钢架、第二部分钢架和第三部分钢架,所述地基桩打地基底部,所述地基板铺设在若干根地基桩上,所述基墩设置在地基板上,所述第一部分钢架安装在基墩上,所述第二部分钢架固定安装在第一部分钢架的顶部,所述第三部分钢架固定安装在第二部分钢架的顶部。本发明的百米烟囱及外部钢制桁架吊装施工工艺可以运用在大型高耸钢结构安装施工中,工艺简单,安全可靠,节约施工成本,底部葫芦提升全部操作位于地上,方便安装与维护,面对突发情况操作性更高,更加安全。
Hundred-meter-high barrel iron chimney steel frame integral hoisting device and process
一种百米高筒体铁质烟囱钢架整体吊装装置及其工艺
CHEN YE (author) / ZHANG YUFEI (author) / LI LIYUAN (author) / HE JIANHUA (author) / LAO JIN (author) / ZHONG WEI (author) / WANG YONGHUA (author) / HUANG TINGGAO (author)
2020-05-01
Patent
Electronic Resource
Chinese
Caisson reinforcing steel bar hoisting and mounting process and hoisting frame
European Patent Office | 2021
|