Method for additionally arranging ring beam and constructional column in existing masonry building body
The invention discloses a method for additionally arranging a ring beam and a constructional column in an existing masonry building body, and relates to the technical field of reinforcement in building bodies. The purpose of reinforcing a wall while reducing the impact on the wall is achieved. According to the technical scheme, the method comprises the steps that S1, drilling is carried out; S2, an anchor rod, a bushing and an exhaust guide pipe are placed into each first placement hole and/or each second placement hole together; S3, cement grouting materials are uniformly stirred with water and poured into the bushing until the slurry overflows the first placement holes and/or the second placement holes; and S4, after the slurry is completely solidified, orifices of the first placement holes and the second placement holes are plugged; S5, each third placement hole communicates with the corresponding two first placement holes or communicates with the corresponding second placement holeand the two first placement holes, each third placement hole is internally provided with a first connector connecting the anchor rods in the corresponding two first placement holes together, or a second connector for connecting the anchor rods in the two first placement holes and the anchor rod in the corresponding second placement hole; and S6, the third placement holes are plugged.
本发明公开一种既有砌体建筑体内增设圈梁和构造柱的方法,涉及建筑体内加固技术领域,达到对墙体进行加固的同时减小对墙体的影响的目的,其技术方案要点是:S1,钻孔;S2,将锚杆、衬套和排气导管一并放入第一放置孔和/或第二放置孔内;S3,将水泥灌浆料用水搅拌均匀,注入衬套内,直至浆液满溢出第一放置孔和/或第二放置孔;S4,浆液完全凝固后对第一放置孔和/或第二放置孔的孔口进行封堵;S5,第三放置孔连通两个第一放置孔或连通第二放置孔和两个第一放置孔,在第三放置孔内设有将两个第一放置孔内锚杆连接在一起的第一连接件,或设有将两个第一放置孔内锚杆以及第二放置孔内锚杆连接在一起的第二连接件;S6,对第三放置孔进行封堵。
Method for additionally arranging ring beam and constructional column in existing masonry building body
The invention discloses a method for additionally arranging a ring beam and a constructional column in an existing masonry building body, and relates to the technical field of reinforcement in building bodies. The purpose of reinforcing a wall while reducing the impact on the wall is achieved. According to the technical scheme, the method comprises the steps that S1, drilling is carried out; S2, an anchor rod, a bushing and an exhaust guide pipe are placed into each first placement hole and/or each second placement hole together; S3, cement grouting materials are uniformly stirred with water and poured into the bushing until the slurry overflows the first placement holes and/or the second placement holes; and S4, after the slurry is completely solidified, orifices of the first placement holes and the second placement holes are plugged; S5, each third placement hole communicates with the corresponding two first placement holes or communicates with the corresponding second placement holeand the two first placement holes, each third placement hole is internally provided with a first connector connecting the anchor rods in the corresponding two first placement holes together, or a second connector for connecting the anchor rods in the two first placement holes and the anchor rod in the corresponding second placement hole; and S6, the third placement holes are plugged.
本发明公开一种既有砌体建筑体内增设圈梁和构造柱的方法,涉及建筑体内加固技术领域,达到对墙体进行加固的同时减小对墙体的影响的目的,其技术方案要点是:S1,钻孔;S2,将锚杆、衬套和排气导管一并放入第一放置孔和/或第二放置孔内;S3,将水泥灌浆料用水搅拌均匀,注入衬套内,直至浆液满溢出第一放置孔和/或第二放置孔;S4,浆液完全凝固后对第一放置孔和/或第二放置孔的孔口进行封堵;S5,第三放置孔连通两个第一放置孔或连通第二放置孔和两个第一放置孔,在第三放置孔内设有将两个第一放置孔内锚杆连接在一起的第一连接件,或设有将两个第一放置孔内锚杆以及第二放置孔内锚杆连接在一起的第二连接件;S6,对第三放置孔进行封堵。
Method for additionally arranging ring beam and constructional column in existing masonry building body
一种既有砌体建筑体内增设圈梁和构造柱的方法
WANG FANGYONG (author) / TAO MING (author) / NIU ENKUAN (author)
2020-09-29
Patent
Electronic Resource
Chinese
IPC:
E04G
SCAFFOLDING
,
Baugerüste
European Patent Office | 2023
|Method for additionally arranging fulcrum column under beam
European Patent Office | 2022
|European Patent Office | 2023
|European Patent Office | 2024
|European Patent Office | 2020
|