The invention discloses a box culvert type concrete structure steel bar modularization and standardization prefabrication and assembly construction process. The process comprises the following steps that step 1, a female die is manufactured; step 2, a reinforcing mesh is manufactured; step 3, the reinforcing mesh is hoisted; step 4, the reinforcing mesh is mounted; and step 5, a guide wall mold and a box type inner mold are installed, and concrete pouring is completed. A traditional construction process of end-to-end connection of formwork construction and steel bar construction is changed into a construction-period-dislocation-free construction process of formwork construction and steel bar construction, a seamless construction flow chain is formed by the construction-period-dislocation-free construction process and pipe gallery modular mold construction, and the construction period is greatly shortened.
本发明的一种箱涵类砼结构钢筋模块化、标准化预制、拼装施工工艺,包括如下步骤:步骤1,制作母模;步骤2,制作钢筋网片;步骤3,钢筋网片的吊装;步骤4,钢筋网片的安装;步骤5,安装导墙模及箱型内模,完成混凝土浇筑。通过将传统支模施工与钢筋施工首尾相接的传统施工工艺,变为支模施工与钢筋施工并驾齐驱的无工期错位施工工艺,与管廊模数化模具施工形成一条无缝施工流水链,大幅缩短施工周期。
Box culvert type concrete structure steel bar modularization and standardization prefabrication and assembly construction process
The invention discloses a box culvert type concrete structure steel bar modularization and standardization prefabrication and assembly construction process. The process comprises the following steps that step 1, a female die is manufactured; step 2, a reinforcing mesh is manufactured; step 3, the reinforcing mesh is hoisted; step 4, the reinforcing mesh is mounted; and step 5, a guide wall mold and a box type inner mold are installed, and concrete pouring is completed. A traditional construction process of end-to-end connection of formwork construction and steel bar construction is changed into a construction-period-dislocation-free construction process of formwork construction and steel bar construction, a seamless construction flow chain is formed by the construction-period-dislocation-free construction process and pipe gallery modular mold construction, and the construction period is greatly shortened.
本发明的一种箱涵类砼结构钢筋模块化、标准化预制、拼装施工工艺,包括如下步骤:步骤1,制作母模;步骤2,制作钢筋网片;步骤3,钢筋网片的吊装;步骤4,钢筋网片的安装;步骤5,安装导墙模及箱型内模,完成混凝土浇筑。通过将传统支模施工与钢筋施工首尾相接的传统施工工艺,变为支模施工与钢筋施工并驾齐驱的无工期错位施工工艺,与管廊模数化模具施工形成一条无缝施工流水链,大幅缩短施工周期。
Box culvert type concrete structure steel bar modularization and standardization prefabrication and assembly construction process
箱涵类砼结构钢筋模块化、标准化预制、拼装施工工艺
XU ZHENJIA (author)
2020-10-30
Patent
Electronic Resource
Chinese
IPC:
E01F
ADDITIONAL WORK, SUCH AS EQUIPPING ROADS OR THE CONSTRUCTION OF PLATFORMS, HELICOPTER LANDING STAGES, SIGNS, SNOW FENCES, OR THE LIKE
,
Zusätzliche Baumaßnahmen, wie die Ausstattung von Straßen oder die bauliche Ausbildung von Bahnsteigen, Landeplätzen für Hubschrauber, Wegweisern, Schneezäunen oder dgl.
/
E04C
STRUCTURAL ELEMENTS
,
Bauelemente
Fabricated box culvert prefabrication system and construction method
European Patent Office | 2024
|Prefabricated square culvert and prefabrication and installation process method thereof
European Patent Office | 2024
|