A platform for research: civil engineering, architecture and urbanism
Walking mechanism and walking method for hanging basket construction device
The invention discloses a walking mechanism for a hanging basket construction device. The mechanism comprises a truss main longitudinal beam which is provided with a plurality of stair stops, a sliding support detachably fixed on a box girder, a front supporting point connected to the truss main longitudinal beam in a sliding manner, and a pushing assembly connected to the truss main longitudinalbeam in the sliding manner. A walking method of the hanging basket construction device comprises the following steps that S1, the sliding support is moved forwards to the position of a next section tobe in place, and the sliding support is anchored, wherein the moving position is as long as a block; S2, a jack is installed, and the front supporting point is jacked and disengaged; S3, a pushing assembly is used for moving the front supporting point forwards to the position of the next section in place; the jack is removed and the front supporting point is anchored; and S4, a hydraulic system is started, and a hydraulic screw and the pushing assembly are used for pushing the hanging basket forwards till the next section is in place. A hanging basket structure can be simplified, mounting anddismounting are convenient, operation walking steps are simplified, on-site construction personnel are reduced, and engineering cost is decreased.
本发明公开了一种用于挂篮施工装置的行走机构,包括桁架主纵梁,该桁架主纵梁配置有若干梯档;还包括滑移支座,可拆卸地固定于箱梁;还包括前支点,滑动连接于该桁架主纵梁;还包括推动组件,滑动连接于该桁架主纵梁。一种挂篮施工装置的行走方法,包括以下步骤,S1将滑移支座前移至下一节段位置就位,锚固滑移支座;移动位置与块件长度相同;S2安装千斤顶,顶升前支点并使前支点脱空;S3利用推动组件将前支点前移至下一节段位置就位;拆除千斤顶,锚固前支点;S4启动液压系统,利用液压螺杆和推动组件向前推动挂篮,直至下一节段位置就位。本发明能够达到简化挂篮构造、安装撤卸方便、操作行走步骤简化,减少现场施工人员,降低工程成本的目的。
Walking mechanism and walking method for hanging basket construction device
The invention discloses a walking mechanism for a hanging basket construction device. The mechanism comprises a truss main longitudinal beam which is provided with a plurality of stair stops, a sliding support detachably fixed on a box girder, a front supporting point connected to the truss main longitudinal beam in a sliding manner, and a pushing assembly connected to the truss main longitudinalbeam in the sliding manner. A walking method of the hanging basket construction device comprises the following steps that S1, the sliding support is moved forwards to the position of a next section tobe in place, and the sliding support is anchored, wherein the moving position is as long as a block; S2, a jack is installed, and the front supporting point is jacked and disengaged; S3, a pushing assembly is used for moving the front supporting point forwards to the position of the next section in place; the jack is removed and the front supporting point is anchored; and S4, a hydraulic system is started, and a hydraulic screw and the pushing assembly are used for pushing the hanging basket forwards till the next section is in place. A hanging basket structure can be simplified, mounting anddismounting are convenient, operation walking steps are simplified, on-site construction personnel are reduced, and engineering cost is decreased.
本发明公开了一种用于挂篮施工装置的行走机构,包括桁架主纵梁,该桁架主纵梁配置有若干梯档;还包括滑移支座,可拆卸地固定于箱梁;还包括前支点,滑动连接于该桁架主纵梁;还包括推动组件,滑动连接于该桁架主纵梁。一种挂篮施工装置的行走方法,包括以下步骤,S1将滑移支座前移至下一节段位置就位,锚固滑移支座;移动位置与块件长度相同;S2安装千斤顶,顶升前支点并使前支点脱空;S3利用推动组件将前支点前移至下一节段位置就位;拆除千斤顶,锚固前支点;S4启动液压系统,利用液压螺杆和推动组件向前推动挂篮,直至下一节段位置就位。本发明能够达到简化挂篮构造、安装撤卸方便、操作行走步骤简化,减少现场施工人员,降低工程成本的目的。
Walking mechanism and walking method for hanging basket construction device
一种用于挂篮施工装置的行走机构及行走方法
MO ZHIQIANG (author) / ZHAO TONG (author) / LIU GANG (author) / WANG YAPING (author) / ZHANG SHENGBO (author) / LI HAI'OU (author) / XIANG ZHIZHOU (author)
2021-03-16
Patent
Electronic Resource
Chinese
IPC:
E01D
BRIDGES
,
Brücken
Walking hanging basket and installing method of walking hanging basket
European Patent Office | 2015
|Front fulcrum hanging basket and hanging basket walking method
European Patent Office | 2023
|Trackless triangular hanging basket walking device and walking method
European Patent Office | 2023
|European Patent Office | 2024
|