Basement outer wall scaffold system and construction method thereof
The invention relates to a basement outer wall scaffold system and a construction method thereof, and belongs to the technical field of scaffolds. The basement outer wall scaffold system comprises transverse rods, longitudinal rods, vertical rods and springboards, one ends, in the length direction, of the transverse rods are fixed through wall connecting pieces detachably connected with a load structure, the ends, away from the load structure, of the transverse rods are connected with a single-row outer frame comprising the longitudinal rods and the vertical rods through fasteners, and the springboards are laid on the adjacent transverse rods. The construction method comprises the steps of material entering, surveying and paying off, frame body erecting and scaffold construction and dismantling. The wall connecting pieces are installed after construction of the load structure is completed, pre-burying is not needed, the fixing position of the transverse rods is conveniently determined, and the transverse rods can be more conveniently installed; and meanwhile, the wall connecting pieces are detachably connected with the load structure, and later-period disassembly of the scaffold is more flexible and efficient.
本申请涉及一种地下室外墙脚手架系统及其施工方法,属于脚手架的技术领域,其包括横杆、纵杆、立杆以及跳板,所述横杆长度方向的一端利用与荷载结构可拆卸连接的连墙件固定,所述横杆远离荷载结构的一端利用扣件与包括纵杆和立杆的单排外架连接,所述跳板铺设在相邻的横杆上;施工方法包括物料进场→测量放线→架体搭设→脚手架施工以及拆除。本申请在荷载结构施工完成后进行连墙件的安装,无需预埋,方便对横杆的固定位置进行确定,能够更方便地安装横杆,同时连墙件与荷载结构可拆卸连接,使脚手架的后期拆卸更加灵活和高效。
Basement outer wall scaffold system and construction method thereof
The invention relates to a basement outer wall scaffold system and a construction method thereof, and belongs to the technical field of scaffolds. The basement outer wall scaffold system comprises transverse rods, longitudinal rods, vertical rods and springboards, one ends, in the length direction, of the transverse rods are fixed through wall connecting pieces detachably connected with a load structure, the ends, away from the load structure, of the transverse rods are connected with a single-row outer frame comprising the longitudinal rods and the vertical rods through fasteners, and the springboards are laid on the adjacent transverse rods. The construction method comprises the steps of material entering, surveying and paying off, frame body erecting and scaffold construction and dismantling. The wall connecting pieces are installed after construction of the load structure is completed, pre-burying is not needed, the fixing position of the transverse rods is conveniently determined, and the transverse rods can be more conveniently installed; and meanwhile, the wall connecting pieces are detachably connected with the load structure, and later-period disassembly of the scaffold is more flexible and efficient.
本申请涉及一种地下室外墙脚手架系统及其施工方法,属于脚手架的技术领域,其包括横杆、纵杆、立杆以及跳板,所述横杆长度方向的一端利用与荷载结构可拆卸连接的连墙件固定,所述横杆远离荷载结构的一端利用扣件与包括纵杆和立杆的单排外架连接,所述跳板铺设在相邻的横杆上;施工方法包括物料进场→测量放线→架体搭设→脚手架施工以及拆除。本申请在荷载结构施工完成后进行连墙件的安装,无需预埋,方便对横杆的固定位置进行确定,能够更方便地安装横杆,同时连墙件与荷载结构可拆卸连接,使脚手架的后期拆卸更加灵活和高效。
Basement outer wall scaffold system and construction method thereof
一种地下室外墙脚手架系统及其施工方法
CHENG LIQIANG (author) / MA YUE (author) / LI SHUN (author) / WEI MIN (author) / ZHANG ZHENG (author) / WANG HUA (author) / ZHANG RUI (author) / SHEN ZE (author) / WANG JIAWEN (author) / LI ZHAO (author)
2021-09-17
Patent
Electronic Resource
Chinese
IPC:
E04G
SCAFFOLDING
,
Baugerüste
Basement outer wall guide wall formwork system and construction method thereof
European Patent Office | 2024
|Basement outer wall waterproof structure and construction method thereof