Lattice column hoisting precision control construction method
The invention provides a lattice column hoisting precision control construction method, which comprises the following steps of: firstly, carrying out survey lofting and site cleaning, firstly cleaning and leveling a site, then carrying out lofting, orienting by using a total station and a theodolite according to a pile position plane graph, a building red line and a survey positioning control point, and determining a pile position point according to the position of the plane graph by using a steel ruler; each pile position point is nailed into the ground through a steel bar coated with red paint, the positioning deviation is smaller than 1 cm, a control cross curve is accurately popped up on the hard terrace, then the pile position is measured, and a recheck sheet is submitted for supervision recheck and acceptance; data are transmitted to a computer, data image forming is carried out by the computer through data transmission, and the computer carries out data image forming, so that the precision can be controlled conveniently. The computer is used for carrying out data image forming, so that comparison operation can be conveniently carried out, comparison can be carried out in the construction process, the installation precision is accurate, the total station is used for observing the installation angle and the drilling position of the drilling machine in the construction process, and the accuracy is improved.
本发明提供了一种格构柱吊装精度控制施工工法,首先进行测量放样和场地清理,先把场地进行清理整平,然后进行放样,根据桩位平面图,建筑红线和测量定位控制点,用全站仪,经纬仪定向,钢尺,按平面图位置确定桩位点,每个桩位点用涂有红漆的钢筋钉入地下,定位偏差小于1cm,并在硬地坪上精确弹出控制十字线,然后测定出桩位并提交复核单供监理复核验收;将数据传送到电脑上,通过数据传送用电脑进行数据图像成型,电脑进行数据图像成型,方便对于精度的掌控。利用电脑进行数据图像成型可以方便进行对比操作,可以在施工的过程中进行对照,使其安装的精度准确,在施工的时候采用全站仪进行观察安装的角度,与钻机钻孔的位置,增加其准确度。
Lattice column hoisting precision control construction method
The invention provides a lattice column hoisting precision control construction method, which comprises the following steps of: firstly, carrying out survey lofting and site cleaning, firstly cleaning and leveling a site, then carrying out lofting, orienting by using a total station and a theodolite according to a pile position plane graph, a building red line and a survey positioning control point, and determining a pile position point according to the position of the plane graph by using a steel ruler; each pile position point is nailed into the ground through a steel bar coated with red paint, the positioning deviation is smaller than 1 cm, a control cross curve is accurately popped up on the hard terrace, then the pile position is measured, and a recheck sheet is submitted for supervision recheck and acceptance; data are transmitted to a computer, data image forming is carried out by the computer through data transmission, and the computer carries out data image forming, so that the precision can be controlled conveniently. The computer is used for carrying out data image forming, so that comparison operation can be conveniently carried out, comparison can be carried out in the construction process, the installation precision is accurate, the total station is used for observing the installation angle and the drilling position of the drilling machine in the construction process, and the accuracy is improved.
本发明提供了一种格构柱吊装精度控制施工工法,首先进行测量放样和场地清理,先把场地进行清理整平,然后进行放样,根据桩位平面图,建筑红线和测量定位控制点,用全站仪,经纬仪定向,钢尺,按平面图位置确定桩位点,每个桩位点用涂有红漆的钢筋钉入地下,定位偏差小于1cm,并在硬地坪上精确弹出控制十字线,然后测定出桩位并提交复核单供监理复核验收;将数据传送到电脑上,通过数据传送用电脑进行数据图像成型,电脑进行数据图像成型,方便对于精度的掌控。利用电脑进行数据图像成型可以方便进行对比操作,可以在施工的过程中进行对照,使其安装的精度准确,在施工的时候采用全站仪进行观察安装的角度,与钻机钻孔的位置,增加其准确度。
Lattice column hoisting precision control construction method
一种格构柱吊装精度控制施工工法
GAO MIN (author) / SHI JIANGUO (author) / WANG CHUNGE (author) / TANG WEIDONG (author) / ZHOU ZHENGGANG (author)
2022-07-05
Patent
Electronic Resource
Chinese
IPC:
E02D
FOUNDATIONS
,
Gründungen
European Patent Office | 2020
|Construction method for hoisting latticed column in place
European Patent Office | 2024
|