Combined water drilling platform system and construction method thereof
The invention discloses a combined type water drilling platform system and a construction method thereof, and relates to the technical field of drilling platforms, the combined type water drilling platform system comprises a first drilling platform and a second drilling platform, the first drilling platform comprises a plurality of steel pipe piles and a bailey beam structure, the plurality of steel pipe piles are inserted on a riverbed or a seabed and are distributed along the periphery of a bearing platform, and the bailey beam structure is arranged on the bearing platform; the bailey beam structure is installed on the multiple steel pipe piles. The second drilling platform comprises a plurality of steel casings and an integral steel structure, the plurality of steel casings are inserted into a riverbed or a seabed and are arranged in the range of the bearing platform, and the integral steel structure is mounted on the plurality of steel casings. The whole water drilling platform system is divided into the first drilling platform and the second drilling platform, the requirements for different using functions and using periods can be better met, the platform engineering amount is greatly reduced, the second drilling platform in the bearing platform area does not need to be provided with temporary supporting steel pipe piles, the construction procedure is simpler and more convenient, and the construction period is shorter.
本发明公开了一种组合式水上钻孔平台系统及其施工方法,涉及钻孔平台技术领域,包括:第一钻孔平台和第二钻孔平台,第一钻孔平台包括多根钢管桩和贝雷梁结构,多根钢管桩插设在河床或海床上,且多根钢管桩沿承台四周布设,贝雷梁结构安装在多根钢管桩上;第二钻孔平台包括多根钢护筒和整体型钢结构,多根钢护筒插设在河床或海床上,且多根钢护筒在承台范围内布设,整体型钢结构安装在多根钢护筒上。本发明将整个水上钻孔平台系统分为第一钻孔平台和第二钻孔平台,能够更好的适应不同使用功能和使用周期的要求,平台工程量大幅降低,且承台区域的第二钻孔平台无需再设置临时支撑钢管桩,施工工序更简便,施工周期更短。
Combined water drilling platform system and construction method thereof
The invention discloses a combined type water drilling platform system and a construction method thereof, and relates to the technical field of drilling platforms, the combined type water drilling platform system comprises a first drilling platform and a second drilling platform, the first drilling platform comprises a plurality of steel pipe piles and a bailey beam structure, the plurality of steel pipe piles are inserted on a riverbed or a seabed and are distributed along the periphery of a bearing platform, and the bailey beam structure is arranged on the bearing platform; the bailey beam structure is installed on the multiple steel pipe piles. The second drilling platform comprises a plurality of steel casings and an integral steel structure, the plurality of steel casings are inserted into a riverbed or a seabed and are arranged in the range of the bearing platform, and the integral steel structure is mounted on the plurality of steel casings. The whole water drilling platform system is divided into the first drilling platform and the second drilling platform, the requirements for different using functions and using periods can be better met, the platform engineering amount is greatly reduced, the second drilling platform in the bearing platform area does not need to be provided with temporary supporting steel pipe piles, the construction procedure is simpler and more convenient, and the construction period is shorter.
本发明公开了一种组合式水上钻孔平台系统及其施工方法,涉及钻孔平台技术领域,包括:第一钻孔平台和第二钻孔平台,第一钻孔平台包括多根钢管桩和贝雷梁结构,多根钢管桩插设在河床或海床上,且多根钢管桩沿承台四周布设,贝雷梁结构安装在多根钢管桩上;第二钻孔平台包括多根钢护筒和整体型钢结构,多根钢护筒插设在河床或海床上,且多根钢护筒在承台范围内布设,整体型钢结构安装在多根钢护筒上。本发明将整个水上钻孔平台系统分为第一钻孔平台和第二钻孔平台,能够更好的适应不同使用功能和使用周期的要求,平台工程量大幅降低,且承台区域的第二钻孔平台无需再设置临时支撑钢管桩,施工工序更简便,施工周期更短。
Combined water drilling platform system and construction method thereof
一种组合式水上钻孔平台系统及其施工方法
MAO WEIQI (author) / LIU JIEWEN (author) / DAI HAO (author) / JIANG BENJUN (author) / TU MANMING (author) / ZHANG DEZHI (author) / ZHANG DONG (author) / HU TENGFEI (author) / ZHAO KUNPENG (author) / WANG NIANCHAO (author)
2022-12-20
Patent
Electronic Resource
Chinese
IPC:
E02B
HYDRAULIC ENGINEERING
,
Wasserbau
Drilling platform in shallow water area and construction method thereof
European Patent Office | 2015
|European Patent Office | 2022
|Cofferdam and drilling platform integrated system and application construction method thereof
European Patent Office | 2022
|European Patent Office | 2022
|