Steel column hoisting device and construction method thereof
According to the steel column hoisting device and the construction method thereof, a plurality of steel columns can be hoisted at the same time in the same period and can be rapidly positioned, and the steel column hoisting device has outstanding advantages under the conditions that the construction period is short and manpower is insufficient. And on the other hand, the position of the steel column is accurately adjusted under the cooperation of a plurality of positioning pieces of the position adjusting assembly, column bottom full penetration welding connection is conducted, the steel column is accurately installed, finally, the sling is lowered through a hoisting machine, the movable sleeve piece is lowered to the bottom of the hoisted steel column, and a constructor can disassemble the movable sleeve piece and the position adjusting assembly together at the lower end of the steel column. In other words, constructors can stand on the floor to complete quick disassembly. The problems that when an existing steel column is installed, workers need to climb up and down on the steel column frequently, and potential safety hazards are large are solved.
本发明公开了一种钢柱吊装装置及其施工方法,在同一周期内可以同时起吊多根钢柱并且快速定位,在面临工期紧张,人力不足的情况下,具有突出的优势。另一方面,钢柱在调位组件的多个定位件的协同配合下精确调整位置,进行柱底全熔透焊接连接,钢柱安装精准,最后通过吊装机械下放吊索,下调活动套件到吊装钢柱的底部,施工人员可以在钢柱的下端将活动套件与调位组件一起拆卸,即施工人员站在楼面即可完成快速拆卸。本发明解决了现有的钢柱安装时需要工人频繁在钢柱上下爬行,安全隐患大的问题。
Steel column hoisting device and construction method thereof
According to the steel column hoisting device and the construction method thereof, a plurality of steel columns can be hoisted at the same time in the same period and can be rapidly positioned, and the steel column hoisting device has outstanding advantages under the conditions that the construction period is short and manpower is insufficient. And on the other hand, the position of the steel column is accurately adjusted under the cooperation of a plurality of positioning pieces of the position adjusting assembly, column bottom full penetration welding connection is conducted, the steel column is accurately installed, finally, the sling is lowered through a hoisting machine, the movable sleeve piece is lowered to the bottom of the hoisted steel column, and a constructor can disassemble the movable sleeve piece and the position adjusting assembly together at the lower end of the steel column. In other words, constructors can stand on the floor to complete quick disassembly. The problems that when an existing steel column is installed, workers need to climb up and down on the steel column frequently, and potential safety hazards are large are solved.
本发明公开了一种钢柱吊装装置及其施工方法,在同一周期内可以同时起吊多根钢柱并且快速定位,在面临工期紧张,人力不足的情况下,具有突出的优势。另一方面,钢柱在调位组件的多个定位件的协同配合下精确调整位置,进行柱底全熔透焊接连接,钢柱安装精准,最后通过吊装机械下放吊索,下调活动套件到吊装钢柱的底部,施工人员可以在钢柱的下端将活动套件与调位组件一起拆卸,即施工人员站在楼面即可完成快速拆卸。本发明解决了现有的钢柱安装时需要工人频繁在钢柱上下爬行,安全隐患大的问题。
Steel column hoisting device and construction method thereof
钢柱吊装装置及其施工方法
ZHANG HENG (author) / WANG DIANQING (author) / BIN YU (author) / LI YANGCHENG (author) / WANG JINPING (author) / ZHAO ZHIWEI (author) / ZHAN FENG (author)
2023-03-21
Patent
Electronic Resource
Chinese