A platform for research: civil engineering, architecture and urbanism
Karst cave filling construction method
The invention discloses a karst cave filling construction method which comprises the steps that firstly, a filling area is scanned, and the position and the size of a karst cave are determined; secondly, according to the position and size of the karst cave, a plurality of grouting pipes arranged at intervals are driven along the edge of the filling area, and the lower ends of the grouting pipes communicate with the upper portion of the karst cave; double-liquid grouting is conducted in the karst cave through the grouting pipe, reactants of the injected double-liquid grouting are gradually stacked from the bottom of the karst cave to the top of the karst cave, and a circle of edge sealing curtain is formed along the edge of the filling area; and finally, after the edge sealing curtain is formed, holes are drilled in the karst cave in the filling area, and filling materials are poured into the karst cave until the filling materials fill the karst cave in the filling area. The method has the effect of reducing the use amount of the filling material during karst cave treatment.
本申请公开了一种溶洞填充施工方法,首先,对填充区域进行扫描,确定溶洞的位置和大小;其次,根据溶洞的位置和大小,沿填充区域的边缘打入多根间隔设置的注浆管,注浆管的下端连通溶洞的上部;通过注浆管往溶洞内进行双液注浆,注入的双液浆的反应物由溶洞底部逐渐堆高直至溶洞顶部,沿填充区域的边缘形成一圈封边帷幕;最后,封边帷幕形成后,往填充区域内的溶洞钻孔并灌注填充材料,直至将填充材料充满填充区域内的溶洞。本申请具有减少溶洞处理时的填充材料用量的效果。
Karst cave filling construction method
The invention discloses a karst cave filling construction method which comprises the steps that firstly, a filling area is scanned, and the position and the size of a karst cave are determined; secondly, according to the position and size of the karst cave, a plurality of grouting pipes arranged at intervals are driven along the edge of the filling area, and the lower ends of the grouting pipes communicate with the upper portion of the karst cave; double-liquid grouting is conducted in the karst cave through the grouting pipe, reactants of the injected double-liquid grouting are gradually stacked from the bottom of the karst cave to the top of the karst cave, and a circle of edge sealing curtain is formed along the edge of the filling area; and finally, after the edge sealing curtain is formed, holes are drilled in the karst cave in the filling area, and filling materials are poured into the karst cave until the filling materials fill the karst cave in the filling area. The method has the effect of reducing the use amount of the filling material during karst cave treatment.
本申请公开了一种溶洞填充施工方法,首先,对填充区域进行扫描,确定溶洞的位置和大小;其次,根据溶洞的位置和大小,沿填充区域的边缘打入多根间隔设置的注浆管,注浆管的下端连通溶洞的上部;通过注浆管往溶洞内进行双液注浆,注入的双液浆的反应物由溶洞底部逐渐堆高直至溶洞顶部,沿填充区域的边缘形成一圈封边帷幕;最后,封边帷幕形成后,往填充区域内的溶洞钻孔并灌注填充材料,直至将填充材料充满填充区域内的溶洞。本申请具有减少溶洞处理时的填充材料用量的效果。
Karst cave filling construction method
一种溶洞填充施工方法
LI ZHIDONG (author) / DENG YASHENG (author) / CAI JIANWEN (author) / LI XIONGRUN (author)
2023-07-07
Patent
Electronic Resource
Chinese
IPC:
E02D
FOUNDATIONS
,
Gründungen
European Patent Office | 2021
|European Patent Office | 2020
|Carrier pile machine compaction karst cave filler and karst cave filling method
European Patent Office | 2020
|High-pressure pre-filling karst cave pile foundation construction method
European Patent Office | 2022
|