A platform for research: civil engineering, architecture and urbanism
Erecting method of shading operation platform for steel column welding construction
The invention relates to the technical field of building construction, in particular to a method for erecting a shading operation platform for steel column welding construction, and the shading operation platform erected by the method is stable in structure, can effectively shield strong light generated in the welding construction process, and is high in practicability. The situation that the daily life of nearby residents is affected by hard light leakage in the welding process is effectively prevented, and environmental light pollution is reduced. After welding construction is completed, a hoisting machine is used for hoisting the two parts of the shading main body carrying the shading cover above the part, the platform plate below the part and the supporting frame upwards, so that the extension section of the vertical rod of the supporting frame is pulled out of the cavity between the channel steel and the surface of the steel column and inserted into the cavity of the channel steel of the next steel column needing to be welded for turnover use. And mounting and dismounting are convenient.
本发明涉及建筑施工技术领域,具体是一种钢柱焊接施工遮光操作平台的搭设方法,采用本发明所述的方法搭设的遮光操作平台,结构稳定,能够有效地遮挡焊接施工过程中产生的强光,有效防止焊接过程中强光外泄影响附近居民的日常生活,减少了环境光污染。焊接施工完成后,使用吊装机械分别将两部分遮光主体携带该部分上方的遮光罩盖、下方的平台板以及支撑架向上吊起,使支撑架竖杆延伸段拔出槽钢与钢柱表面之间的空腔,插接到下一个需要焊接的钢柱槽钢空腔内,周转使用,安装、拆卸较为便捷。
Erecting method of shading operation platform for steel column welding construction
The invention relates to the technical field of building construction, in particular to a method for erecting a shading operation platform for steel column welding construction, and the shading operation platform erected by the method is stable in structure, can effectively shield strong light generated in the welding construction process, and is high in practicability. The situation that the daily life of nearby residents is affected by hard light leakage in the welding process is effectively prevented, and environmental light pollution is reduced. After welding construction is completed, a hoisting machine is used for hoisting the two parts of the shading main body carrying the shading cover above the part, the platform plate below the part and the supporting frame upwards, so that the extension section of the vertical rod of the supporting frame is pulled out of the cavity between the channel steel and the surface of the steel column and inserted into the cavity of the channel steel of the next steel column needing to be welded for turnover use. And mounting and dismounting are convenient.
本发明涉及建筑施工技术领域,具体是一种钢柱焊接施工遮光操作平台的搭设方法,采用本发明所述的方法搭设的遮光操作平台,结构稳定,能够有效地遮挡焊接施工过程中产生的强光,有效防止焊接过程中强光外泄影响附近居民的日常生活,减少了环境光污染。焊接施工完成后,使用吊装机械分别将两部分遮光主体携带该部分上方的遮光罩盖、下方的平台板以及支撑架向上吊起,使支撑架竖杆延伸段拔出槽钢与钢柱表面之间的空腔,插接到下一个需要焊接的钢柱槽钢空腔内,周转使用,安装、拆卸较为便捷。
Erecting method of shading operation platform for steel column welding construction
一种钢柱焊接施工遮光操作平台的搭设方法
FENG KUNKUN (author) / SONG YANFEI (author) / CI GUOQIANG (author)
2023-10-10
Patent
Electronic Resource
Chinese
IPC:
E04G
SCAFFOLDING
,
Baugerüste
Building construction operation platform and erecting method
European Patent Office | 2023
|Assembly type large X steel pipe column welding construction operation platform
European Patent Office | 2023
|Method for erecting masonry construction operation platform in elevator shaft
European Patent Office | 2021
|Formwork erecting construction method for closed constructional column
European Patent Office | 2023
|European Patent Office | 2022
|