Cover beam construction device and construction process thereof
The invention relates to a capping beam construction device and a construction process thereof. The capping beam construction device is installed on a stand column, and a positioning pin hole is formed in the side face of the stand column; the device is characterized by comprising a crawling trolley, an elevation fine adjustment jack, a side template, a bottom template, a lower distribution beam and a lifting module, the specific process comprises the steps that S1, the crawling trolley is arranged; s2, mounting a bottom mold, a side mold and an operation platform; s3, the lifting module and the lowering module are installed; the bottom formwork, the side formworks and the operating platform can be assembled in place at a time on the ground, high-altitude hoisting operation is little, hoisting machines are rarely used in the construction period, and the construction cost is reduced; in addition, in the capping beam construction device, the dangerous operation procedures of mounting and dismounting a hoop or a penetrating steel bar are omitted, the safety is greatly improved, and the construction efficiency is improved.
本发明涉及一种盖梁施工装置及其施工工艺,该盖梁施工装置安装在立柱,且立柱的侧面上设置有定位销孔;其特征在于:包括爬行小车、标高微调千斤顶、侧模板、底模板、下分配梁和升降模块;具体工艺包括:S1:爬行小车的设置;S2:底、侧模及操作平台安装;S3:提升、下放模块的安装;底模板、侧模板以及操作的平台在地面处可实现一次拼装到位,高空吊装作业少,且施工周期中很少用到吊装机械,降低了施工成本;此外,本盖梁施工装置中省去了安装、拆除抱箍或穿心钢棒的较危险的作业工序,极大的提升了安全性,提高了施工效率。
Cover beam construction device and construction process thereof
The invention relates to a capping beam construction device and a construction process thereof. The capping beam construction device is installed on a stand column, and a positioning pin hole is formed in the side face of the stand column; the device is characterized by comprising a crawling trolley, an elevation fine adjustment jack, a side template, a bottom template, a lower distribution beam and a lifting module, the specific process comprises the steps that S1, the crawling trolley is arranged; s2, mounting a bottom mold, a side mold and an operation platform; s3, the lifting module and the lowering module are installed; the bottom formwork, the side formworks and the operating platform can be assembled in place at a time on the ground, high-altitude hoisting operation is little, hoisting machines are rarely used in the construction period, and the construction cost is reduced; in addition, in the capping beam construction device, the dangerous operation procedures of mounting and dismounting a hoop or a penetrating steel bar are omitted, the safety is greatly improved, and the construction efficiency is improved.
本发明涉及一种盖梁施工装置及其施工工艺,该盖梁施工装置安装在立柱,且立柱的侧面上设置有定位销孔;其特征在于:包括爬行小车、标高微调千斤顶、侧模板、底模板、下分配梁和升降模块;具体工艺包括:S1:爬行小车的设置;S2:底、侧模及操作平台安装;S3:提升、下放模块的安装;底模板、侧模板以及操作的平台在地面处可实现一次拼装到位,高空吊装作业少,且施工周期中很少用到吊装机械,降低了施工成本;此外,本盖梁施工装置中省去了安装、拆除抱箍或穿心钢棒的较危险的作业工序,极大的提升了安全性,提高了施工效率。
Cover beam construction device and construction process thereof
一种盖梁施工装置及其施工工艺
LIU LIANGLIANG (author) / FU LUNPENG (author)
2024-02-09
Patent
Electronic Resource
Chinese
IPC:
E01D
BRIDGES
,
Brücken