Underwater steel pipe pile dismantling device and method
The invention discloses an underwater steel pipe pile dismantling device and method, and relates to the technical field of bridge construction. The underwater steel pipe pile dismantling device comprises a supporting assembly used for being arranged above a bridge, a platform assembly used for being arranged below the bridge and two connecting assemblies used for being arranged on the two sides of the bridge, and the two ends of each connecting assembly are connected with the supporting assembly and the platform assembly correspondingly. And a pile pulling assembly is arranged on the platform assembly. The underwater steel pipe pile dismantling device provided by the embodiment of the invention is used for dismantling the underwater steel pipe pile, and compared with the prior art, the underwater steel pipe pile dismantling device is not affected by tide fluctuation and river water flow velocity, the whole steel pipe pile can be pulled out, later river channel excavation is facilitated, direct underwater cutting is avoided, and the safety of operators is improved.
本申请公开了一种水下钢管桩拆除装置及方法,涉及桥梁施工技术领域。该水下钢管桩拆除装置,包括用于设置在桥梁上方的支撑组件、用于设置在所述桥梁下方的平台组件和两个用于布置在所述桥梁两侧的连接组件,所述连接组件的两端分别与所述支撑组件和所述平台组件连接,所述平台组件上设置有拔桩组件。本申请实施例提供的水下钢管桩拆除装置,用于拆除水下钢管桩,与现有技术相比,不受潮水涨落、河水流速的影响,能够将整个钢管桩拔出,有利于后期河道的开挖,而且避免了直接水下切割,提高了操作人员的安全性。
Underwater steel pipe pile dismantling device and method
The invention discloses an underwater steel pipe pile dismantling device and method, and relates to the technical field of bridge construction. The underwater steel pipe pile dismantling device comprises a supporting assembly used for being arranged above a bridge, a platform assembly used for being arranged below the bridge and two connecting assemblies used for being arranged on the two sides of the bridge, and the two ends of each connecting assembly are connected with the supporting assembly and the platform assembly correspondingly. And a pile pulling assembly is arranged on the platform assembly. The underwater steel pipe pile dismantling device provided by the embodiment of the invention is used for dismantling the underwater steel pipe pile, and compared with the prior art, the underwater steel pipe pile dismantling device is not affected by tide fluctuation and river water flow velocity, the whole steel pipe pile can be pulled out, later river channel excavation is facilitated, direct underwater cutting is avoided, and the safety of operators is improved.
本申请公开了一种水下钢管桩拆除装置及方法,涉及桥梁施工技术领域。该水下钢管桩拆除装置,包括用于设置在桥梁上方的支撑组件、用于设置在所述桥梁下方的平台组件和两个用于布置在所述桥梁两侧的连接组件,所述连接组件的两端分别与所述支撑组件和所述平台组件连接,所述平台组件上设置有拔桩组件。本申请实施例提供的水下钢管桩拆除装置,用于拆除水下钢管桩,与现有技术相比,不受潮水涨落、河水流速的影响,能够将整个钢管桩拔出,有利于后期河道的开挖,而且避免了直接水下切割,提高了操作人员的安全性。
Underwater steel pipe pile dismantling device and method
一种水下钢管桩拆除装置及方法
TANG XING (author) / LUO LI (author) / QIN YONGKE (author) / WANG JIALIN (author) / ZHANG LINGXI (author) / LI WEI (author) / LIU JUNLIANG (author)
2024-07-02
Patent
Electronic Resource
Chinese
IPC:
E02D
FOUNDATIONS
,
Gründungen
Construction method of cast-in-place bridge steel pipe pile underwater support dismantling system
European Patent Office | 2022