Construction method for connecting bottom plate and basement top plate in high-proportion non-basement area
The invention relates to a construction method for connecting a bottom plate with a basement top plate in a high-proportion non-basement area. The construction method comprises the following steps that the bottom plate outside a set distance range outside a basement setting area is constructed; foundation pit supporting and earth excavation of the basement setting area are synchronously constructed to form a foundation pit of the basement; constructing a basement bottom plate, a basement outer wall and a basement top plate at the bottom of the foundation pit; when the basement top plate is constructed, steel bar connectors are arranged on the corresponding side faces of the basement top plate; fertilizer groove backfilling is conducted on the outer side of the basement outer wall; a fender post for foundation pit supporting is pulled out; connecting steel bars are arranged between the bottom plate and the basement top plate, and concrete is poured at the connecting steel bars to complete connecting construction of the bottom plate and the basement top plate in the non-basement area. According to the method, part of the bottom plate (namely the bottom plate outside the set distance range) of the basement-free area and the basement are synchronously constructed, subsequent connection construction is conducted at the reserved connecting position, and the construction progress and efficiency can be better controlled.
本发明涉及一种高占比无地下室区域的底板与地下室顶板连接的施工方法,包括如下步骤:施工地下室设置区域外设定距离范围外的底板;同步施工地下室设置区域的基坑支护及土方开挖以形成地下室的基坑;在基坑底部施工地下室底板、地下室外墙以及地下室顶板;施工地下室顶板时,在地下室顶板对应的侧面设置钢筋接驳器;在地下室外墙的外侧进行肥槽回填;拔出基坑支护用的围护桩;在底板和地下室顶板之间设置连接钢筋,并在连接钢筋处浇筑混凝土以完成无地下室区域的底板与地下室顶板的连接施工。本发明同步施工无地下室区域的部分底板(也即设定距离范围外的底板)和地下室,预留连接处进行后续的连接施工,能够更好的控制施工进度和效率。
Construction method for connecting bottom plate and basement top plate in high-proportion non-basement area
The invention relates to a construction method for connecting a bottom plate with a basement top plate in a high-proportion non-basement area. The construction method comprises the following steps that the bottom plate outside a set distance range outside a basement setting area is constructed; foundation pit supporting and earth excavation of the basement setting area are synchronously constructed to form a foundation pit of the basement; constructing a basement bottom plate, a basement outer wall and a basement top plate at the bottom of the foundation pit; when the basement top plate is constructed, steel bar connectors are arranged on the corresponding side faces of the basement top plate; fertilizer groove backfilling is conducted on the outer side of the basement outer wall; a fender post for foundation pit supporting is pulled out; connecting steel bars are arranged between the bottom plate and the basement top plate, and concrete is poured at the connecting steel bars to complete connecting construction of the bottom plate and the basement top plate in the non-basement area. According to the method, part of the bottom plate (namely the bottom plate outside the set distance range) of the basement-free area and the basement are synchronously constructed, subsequent connection construction is conducted at the reserved connecting position, and the construction progress and efficiency can be better controlled.
本发明涉及一种高占比无地下室区域的底板与地下室顶板连接的施工方法,包括如下步骤:施工地下室设置区域外设定距离范围外的底板;同步施工地下室设置区域的基坑支护及土方开挖以形成地下室的基坑;在基坑底部施工地下室底板、地下室外墙以及地下室顶板;施工地下室顶板时,在地下室顶板对应的侧面设置钢筋接驳器;在地下室外墙的外侧进行肥槽回填;拔出基坑支护用的围护桩;在底板和地下室顶板之间设置连接钢筋,并在连接钢筋处浇筑混凝土以完成无地下室区域的底板与地下室顶板的连接施工。本发明同步施工无地下室区域的部分底板(也即设定距离范围外的底板)和地下室,预留连接处进行后续的连接施工,能够更好的控制施工进度和效率。
Construction method for connecting bottom plate and basement top plate in high-proportion non-basement area
高占比无地下室区域的底板与地下室顶板连接的施工方法
ZHONG SHUWEN (author) / ZHANG XIAOBIN (author) / HUANG PEILIN (author) / WENG MINMIN (author) / ZHONG YI (author) / XIE CHUANYI (author) / ZUO MEIKUN (author)
2024-11-26
Patent
Electronic Resource
Chinese
Water drainage structure of basement bottom plate and construction method of basement bottom plate
European Patent Office | 2022
|Basement bottom plate structure and construction method thereof
European Patent Office | 2020
|Anti-seepage construction method for basement bottom plate
European Patent Office | 2023
|