A platform for research: civil engineering, architecture and urbanism
FORM INSTALLATION METHOD, FORM AND UNDERWATER STRUCTURE
PROBLEM TO BE SOLVED: To provide a form installation method and the like, which can reduce underwater work and which make a form easily self-supportable.SOLUTION: A drilled hole 9 is formed in a water bottom 21, and a sheath pipe 11 is installed in the drilled hole 9. A form 1, in which adjacent form panels 3 are connected together by a steel pipe pile 5, is arranged by inserting a pipe part 5b of the steel pipe pile 5 into the sheath pipe 11. In addition, wire nets 27 and 29 provided in the form panel 3 are stretched to close a gap between the form 1 and the water bottom 21 and a gap between the form 1 and a wall surface of a dam body 2. Furthermore, concrete 7 is injected from inside the steel pipe pile 5, and the drilled hole 9 is filled with the concrete 7 via a hole 15 of the pile part 5b and a hole 13 of the sheath pipe 11 so that consolidation of foundation can be performed.
【課題】水中作業の軽減が可能であり、型枠が容易に自立可能な型枠設置方法等を提供する。【解決手段】水底21に掘削孔9を形成して、掘削孔9に鞘管11を設置する。そして、隣り合う型枠パネル3を鋼管杭5で連結した型枠1を、鞘管11内に鋼管杭5の杭部5bを挿入して配置する。また、型枠パネル3に設けた金網27、29を広げ、型枠1と水底21の間の隙間、型枠1と堤体2の壁面との間の隙間を塞ぐ。さらに、鋼管杭5の内部からコンクリート7を注入し、杭部5bの孔15と鞘管11の孔13を介して、掘削孔9にコンクリート7を充填して根固めを行う。【選択図】図5
FORM INSTALLATION METHOD, FORM AND UNDERWATER STRUCTURE
PROBLEM TO BE SOLVED: To provide a form installation method and the like, which can reduce underwater work and which make a form easily self-supportable.SOLUTION: A drilled hole 9 is formed in a water bottom 21, and a sheath pipe 11 is installed in the drilled hole 9. A form 1, in which adjacent form panels 3 are connected together by a steel pipe pile 5, is arranged by inserting a pipe part 5b of the steel pipe pile 5 into the sheath pipe 11. In addition, wire nets 27 and 29 provided in the form panel 3 are stretched to close a gap between the form 1 and the water bottom 21 and a gap between the form 1 and a wall surface of a dam body 2. Furthermore, concrete 7 is injected from inside the steel pipe pile 5, and the drilled hole 9 is filled with the concrete 7 via a hole 15 of the pile part 5b and a hole 13 of the sheath pipe 11 so that consolidation of foundation can be performed.
【課題】水中作業の軽減が可能であり、型枠が容易に自立可能な型枠設置方法等を提供する。【解決手段】水底21に掘削孔9を形成して、掘削孔9に鞘管11を設置する。そして、隣り合う型枠パネル3を鋼管杭5で連結した型枠1を、鞘管11内に鋼管杭5の杭部5bを挿入して配置する。また、型枠パネル3に設けた金網27、29を広げ、型枠1と水底21の間の隙間、型枠1と堤体2の壁面との間の隙間を塞ぐ。さらに、鋼管杭5の内部からコンクリート7を注入し、杭部5bの孔15と鞘管11の孔13を介して、掘削孔9にコンクリート7を充填して根固めを行う。【選択図】図5
FORM INSTALLATION METHOD, FORM AND UNDERWATER STRUCTURE
型枠設置方法、型枠および水中構造物
TAKIGUCHI NORIO (author) / SUZUKI SATOSHI (author) / FUJIWARA KENZO (author) / KITAZAKI SHINJI (author) / TAKADA ETSUHISA (author) / NISHIO AKIRA (author) / OGURA TSUYOSHI (author) / IIDA KAZUHIRO (author)
2015-09-24
Patent
Electronic Resource
Japanese
FORM STRUCTURE AND FORM INSTALLATION METHOD FOR COLUMNAR STRUCTURE
European Patent Office | 2024
|UNDERWATER STRUCTURE INSTALLATION DEVICE AND INSTALLATION METHOD
European Patent Office | 2016
|