A platform for research: civil engineering, architecture and urbanism
GROUT MATERIAL FILLING METHOD AND SYSTEM
PROBLEM TO BE SOLVED: To prevent damaging of a pump and pipeline, without leaving a void in an insertion hole.SOLUTION: A grout material filling system 1 of the present invention includes a bottom mold 2 installed on an opening 8 of an insertion hole 7 formed almost vertically upward on a reinforced concrete building frame 6, and a booster pump 5 communicated and connected with an injection port 3 provided on the bottom mold, through injection pipeline 4. The bottom mold 2 is configured to block outflow of mortar from the insertion hole 7 through an air vent port 11 after an air vent material 10 has been pulled out from the air vent port, as well as outflow of mortar from the insertion hole 7 through the injection port 3. A relief valve 13 is provided on the injection pipeline 4 as pressure adjustment means, the relief valve discharging the grout material outside of the injection pipeline 4 only when pressure of the grout material inside the injection pipeline 4 exceeds a preset value.SELECTED DRAWING: Figure 1
【課題】挿入穴に空隙を残すことなく、ポンプや配管類の破損を防止する。【解決手段】本発明に係るグラウト材充填システム1は、鉄筋コンクリート躯体6にほぼ鉛直上向きに形成された挿入穴7の開口8に設置される底型枠2と、該底型枠に設けられた注入口3に注入用部材としての注入用配管4を介して連通接続された加圧ポンプ5とを備え、底型枠2は、エア抜き部材10をエア抜き口11から引き抜いた後の該エア抜き口を介した挿入穴7からのモルタルの流出や、注入口3を介した挿入穴7からのモルタルの流出を遮断できるように構成してあるとともに、注入用配管4には圧力調整手段としてのリリーフ弁13を設けてあり、該リリーフ弁は、注入用配管4内のグラウト材の圧力が設定値を上回ったときのみ該グラウト材を注入用配管4の外に排出するようになっている。【選択図】 図1
GROUT MATERIAL FILLING METHOD AND SYSTEM
PROBLEM TO BE SOLVED: To prevent damaging of a pump and pipeline, without leaving a void in an insertion hole.SOLUTION: A grout material filling system 1 of the present invention includes a bottom mold 2 installed on an opening 8 of an insertion hole 7 formed almost vertically upward on a reinforced concrete building frame 6, and a booster pump 5 communicated and connected with an injection port 3 provided on the bottom mold, through injection pipeline 4. The bottom mold 2 is configured to block outflow of mortar from the insertion hole 7 through an air vent port 11 after an air vent material 10 has been pulled out from the air vent port, as well as outflow of mortar from the insertion hole 7 through the injection port 3. A relief valve 13 is provided on the injection pipeline 4 as pressure adjustment means, the relief valve discharging the grout material outside of the injection pipeline 4 only when pressure of the grout material inside the injection pipeline 4 exceeds a preset value.SELECTED DRAWING: Figure 1
【課題】挿入穴に空隙を残すことなく、ポンプや配管類の破損を防止する。【解決手段】本発明に係るグラウト材充填システム1は、鉄筋コンクリート躯体6にほぼ鉛直上向きに形成された挿入穴7の開口8に設置される底型枠2と、該底型枠に設けられた注入口3に注入用部材としての注入用配管4を介して連通接続された加圧ポンプ5とを備え、底型枠2は、エア抜き部材10をエア抜き口11から引き抜いた後の該エア抜き口を介した挿入穴7からのモルタルの流出や、注入口3を介した挿入穴7からのモルタルの流出を遮断できるように構成してあるとともに、注入用配管4には圧力調整手段としてのリリーフ弁13を設けてあり、該リリーフ弁は、注入用配管4内のグラウト材の圧力が設定値を上回ったときのみ該グラウト材を注入用配管4の外に排出するようになっている。【選択図】 図1
GROUT MATERIAL FILLING METHOD AND SYSTEM
グラウト材充填方法及びシステム
TANAKA KOICHI (author) / HIRAGA TOMOKO (author) / KASAGI RYOJI (author)
2018-06-21
Patent
Electronic Resource
Japanese
IPC:
E04G
SCAFFOLDING
,
Baugerüste
FILLING EVALUATION METHOD OF GROUT MATERIAL AND FILLING EVALUATION MEMBER OF GROUT MATERIAL
European Patent Office | 2018
|