REPAIR METHOD FOR FILLER LAYER OF CONCRETE SLAB TRACK
To provide a repair method for a concrete slab track which can repair in a short time, the CA mortar layer in an existing concrete slab track.SOLUTION: A repair method for a filler layer in a concrete slab track, which digs the filler layer located between a roadbed concrete and a track concrete slab in the concrete slab track from a side of the concrete slab track and filling a repair material therein, comprises: a first step of digging the filler layer down to a designated depth from the side of the concrete slab track; a second step of inserting pre-made blocks with a designated shape having strength greater than a prescribed level as a repair material into the space dug during said first step; and a third step of performing a subsequent treatment to prevent the blocks inserted into said space from coming out.SELECTED DRAWING: Figure 2
【課題】既設のスラブ軌道において短時間にCAモルタル層を補修することができるスラブ軌道の補修方法を提供する。【解決手段】スラブ軌道において路盤コンクリートと軌道スラブの間に設けられている填充層を、スラブ軌道の側方から掘削して補修材を充填するスラブ軌道における填充層の補修方法において、前記填充層をスラブ軌道の側方から所定の奥行深さまで掘削する第1工程と、予め製造された所定形状および所定以上の強度を有するブロックを補修材として前記第1工程により掘削された部位に挿入する第2工程と、前記部位に挿入された前記ブロックが抜け出さないように後処理を行う第3工程と、を含むようにした。【選択図】図2
REPAIR METHOD FOR FILLER LAYER OF CONCRETE SLAB TRACK
To provide a repair method for a concrete slab track which can repair in a short time, the CA mortar layer in an existing concrete slab track.SOLUTION: A repair method for a filler layer in a concrete slab track, which digs the filler layer located between a roadbed concrete and a track concrete slab in the concrete slab track from a side of the concrete slab track and filling a repair material therein, comprises: a first step of digging the filler layer down to a designated depth from the side of the concrete slab track; a second step of inserting pre-made blocks with a designated shape having strength greater than a prescribed level as a repair material into the space dug during said first step; and a third step of performing a subsequent treatment to prevent the blocks inserted into said space from coming out.SELECTED DRAWING: Figure 2
【課題】既設のスラブ軌道において短時間にCAモルタル層を補修することができるスラブ軌道の補修方法を提供する。【解決手段】スラブ軌道において路盤コンクリートと軌道スラブの間に設けられている填充層を、スラブ軌道の側方から掘削して補修材を充填するスラブ軌道における填充層の補修方法において、前記填充層をスラブ軌道の側方から所定の奥行深さまで掘削する第1工程と、予め製造された所定形状および所定以上の強度を有するブロックを補修材として前記第1工程により掘削された部位に挿入する第2工程と、前記部位に挿入された前記ブロックが抜け出さないように後処理を行う第3工程と、を含むようにした。【選択図】図2
REPAIR METHOD FOR FILLER LAYER OF CONCRETE SLAB TRACK
スラブ軌道における填充層の補修方法
SATO SAKI (author) / KOZU DAISUKE (author)
2022-10-27
Patent
Electronic Resource
Japanese